Attachment 6 - Stormwater Management Plan
The original of this document is very large (26.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnR2015: NOOSA LANDFILL - STORMWATER MANAGEMENT PLAN
1.5. PRINCIPLES OF SURFACE WATER MANAGEMENT FOR THE SITE
Ongoing soil and water management will be required through the life of the project. The three cornerstones of the
erosion and sediment control industry are drainage control, erosion control, and sediment control. The primary function
of each of these principles is summarised below:
+ Drainage control measures aim to prevent or reduce soil erosion caused by concentrated flow-including the
management of rill and gully erosion and to appropriately manage the movement of "clean" and "dirty" water
through the site.
+ Erosion control measures aim to prevent or reduce soil erosion caused by raindrop impact and sheet flow (i.e.
the control of splash and sheet erosion)
+ Sediment control measures aim to trap and retain sediment either moving along the land surface (bed load) or
contained within flowing water (suspended sediment) (IECA, 2008).
The proper management of stormwater is critical to the implementation of effective erosion and sediment control. The
effective management of stormwater lies in the appropriate control of runoff velocities and volume.
1.6. DRAINAGE CONTROL
The primary function drainage controls are to:
+ minimise the risk of rill and gully erosion;
+ minimise the risk of hydraulic damage to the adopted erosion and sediment control measures;
+ control the velocity, volume and location of water flow through the site; and
+ appropriately manage the movement of "clean" and "dirty" water through the site (IECA, 2008).
The Guideline - Stormwater and environmentally relevant activities (DES, 2021) requires that high erosion hazard sites
implement the following design and management measures:
+ Erosion protection and sediment control measures should be installed and maintained for all stages of the
activity to minimise erosion and the release of sediments.
+ All areas of soil disturbed and exposed should be managed to minimise the loss of sediment through
revegetation and/or use of other stabilisation techniques.
+ All concentrated stormwater flows (including ‘clean’ stormwater and ‘dirty’ stormwater) should have
concentrated flow paths, such as drainage lines, diversion drains, channels and batter chutes (where applicable)
which have been designed, constructed, effectively armoured and maintained to convey the runoff from events
up to and including the average recurrence interval (ARI) of:
o 1 in 10 year critical duration ARI storm event without causing water contamination, sheet, rill or gully
erosion, sedimentation, or damage to structures or property.
+ Stormwater runoff from external or undisturbed catchments should be diverted around or away from disturbed
areas as much as possible.
+ Sediment basin(s) should be installed and maintained to collect and treat stormwater runoff from all disturbed
areas of the site(s) approved as part of the ERA application, and areas in which any earthen material is stored.
+ For events up to and including a 24 hour storm event with an ARI of 1 in 10 years, the following must be achieved
o a sediment basin must be designed, constructed and operated to retain the runoff at the site(s)
approved as part of the ERA application;
o the release stormwater from these sediment basins must achieve a total suspended solids (TSS)
concentration of no more than 50mg/L for events up to and including those mentioned above.
For events larger than those stated above, all reasonable and practical measures must be taken to minimise the
release of prescribed contaminants.
An alternative basin design (such as a high efficiency basin) can be used provided it has been demonstrated
that the contaminant load to be released to the receiving environment for the life of the project will be equal to
or less than the standard design.
The department supports high efficiency basin technology especially as it may lead to both flexibility
for the site operator and if appropriately designed and managed, sound environmental outcomes.
+ All sediment basins should have a spillway, designed, constructed and effectively armoured to convey
anticipated flows. Design for a 50 year ARI critical event is considered a minimum.
+ Any sediment basin designed in accordance with this list must be operated in such a manner that within 120
hours of the most recent rainfall event, the required design capacity of the upper settling volume is available for
capture and storage of stormwater runoff from the next rainfall event.
Environment. Engineering. Education. PAGE 4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.