27. Pedestrian and bicycle facilities must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and must
include in particular:
a. a 2 metre wide concrete footpath within the road verge for the entire length of
the site’s frontage to Eumundi Noosa Road
b. a 1.5m wide concrete footpath within the road verge for the entire length of the
site’s frontage to Lionel Donovan Drive and extending to join to the existing
footpath to the south-west.
c. signage and lighting at strategic locations to direct people to building entries
d. pedestrian refuge areas at strategic locations within the carpark to ensure safe
and convenient congregating of pedestrians waiting to cross major access
driveways.
This condition is imposed pursuant to s665 of the Sustainable Planning Act 2009
being non-trunk infrastructure.
28. A total of 15 bicycle parking spaces and suitable end of trip bicycle facilities must be
provided for the development. End of trip facilities must be provided at the following
rate:
a. 1 locker per 2 bicycle spaces
b. 1 shower cubicle with ancillary change room per 10 bicycle spaces or part
thereof.
Stormwater Drainage
29. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and be generally in accordance with the Stormwater Management
Plan – Report No F0002-AA007595-AAR-05 – dated 30 March 2015 prepared by
Hyder.
Stormwater Quality Management
a. A stormwater quality treatment system must be provided for the development.
The works must be undertaken in accordance with an Operational Works
approval and the Bioretention Technical Design Guidelines (Water by Design,
2012), and must include in particular bioretention devices which:
i. are designed generally in accordance with IPWEQA Standard Drawing
No. WSUD-001
ii. are provided with a free-draining outlet from the sub-soil drainage system
iii. swales which are designed in accordance with the Water Sensitive
Urban Design Technical Design Guidelines for South East Queensland.
30. All stormwater quality treatment devices must be maintained in accordance with the
Water by Design (2009) - Maintaining Vegetated Stormwater Assets (Version 1). A
copy of this document must be retained on the site together with the approved
Operational Works drawings for the stormwater quality treatment system and a
detailed life cycle costing of the system attached as an addendum. Records of all
maintenance activities undertaken must be kept and made available to Council upon
request.
Page 8 of 171
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.