SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 7 MARCH 2023
Capital Works Executive meetings. The Schedule
of Rates have been confirmed by the contractor.
Material price increases Council will engage contractor under schedule of
rates contract with locked in material rates not
subject to rise and fall. The Schedule of Rates
have been confirmed by the contractor.
Contractor becomes insolvent Council has not carried out a financial viability
check on the preferred contractor as the original
project estimate was less than the Financial
Capability guideline tolerances. The contractor is
a well-established contractor.
Program Risks Mitigation
Resource risk The contractor has nominated a capable and
experienced project team to undertake
construction. Council’s resources to the project
will be monitored by the Project Control Group and
Capital Works Executive due to the high volume
of work in the capital works program.
Construction takes longer than allowed for The contractor is well resourced and has the
available resources to deliver this project
successfully. The risk is mitigated through the
contract, and will be closely monitored by the
Contract Administrator.
Grant funding bodies and Council will be
consulted to manage any variations to
agreements that may arise.
Lead time of materials pushing the program out Many associated risks are mitigated by ordering
the materials as soon as possible after the
contract award. The contractor is aware and will
manage this risk and work closely together with
Council's project team to minimise residual timing
risk. The Schedule of Rates have been confirmed
by the contractor.
Safety Risks Mitigation
The Contractor fails to ensure the work is Prior to commencement of works, contractor will
conducted safely and in accordance with ensure management plans, Safe Work Method
minimum standards Statements, Job Hazard Analysis (or similar), and
other documentation are submitted, reviewed, and
accepted by Council.
Council will undertake surveillance, regular safety
audits and inspections throughout the
construction period.
Environment Harm Risks Mitigation
Works impact on the environment The contractor will have a site environmental
management plan to identify and manage site
specific risks.
Scope & Quality Risks Mitigation
Risk of not meeting project objectives Compliance with project objectives will be
managed through regular reviews of the
contractor’s design and construction by the
Contract Administrator and other project team
members as required.
Page 25 of 35
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.