SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 7 MARCH 2023
panel confirmed Telstra’s ability to undertake the works and meet the specifications and
requirements. Telstra’s tender submission demonstrated the following:
• A high level of previous experience undertaking projects of similar size and scope for other
councils, most recently Toowoomba Regional Council and Mornington Shire Council;
• Provided a detailed design and construction methodology and programme which aligns
to the contract specifications;
• Adequately resourced with key personnel and sub-contract suppliers, specifically Simoco
who are an Australian based manufacturer and systems integrator of critical
communications solutions across a broad range of technologies;
• Certified carbon neutral in every aspect of the business with very strong policy, compliant
with global reporting initiatives, resource efficiency targets, and includes sustainability in
the value chain. Environmental Management System (ISO 14001:2015) compliant;
• Certified Quality Management system (ISO 9001:2015);
• Workplace Health and Safety system (AS/NZS 4801:2001) compliant;
• Comprehensive policies and procedures to manage safety, quality and environmental
impacts throughout the contract.
3. Next Steps
Once awarded, the Design, Supply, Install and Service a Digital Two-Way Radio System with
GPS Location Service will commence upon mobilisation, at date to be advised, with the aim to
achieve practical completion by the end of December 2023. The contract will include a 12-month
servicing and maintenance period to commence at the satisfactory completion of the radio and
GPS system implementation.
Previous Council Consideration
Nil
Finance
Initial project budget of $778k was fully funded via the QRA’s Black Summer Bushfire Recovery
Grant Program for investment into projects that build resilience in areas affected by the 2019-
20 bushfires.
The proposed tender acceptance price, subject to final contract negotiation, is approximately
$484k higher than budget and grant allocation (set in 2020 as part of the grant application) due
to market factors and specification requirements to ensure sufficient network coverage.
It is proposed that the initial shortfall will be funded initially from Council’s Fleet Replacement
Program Budget which is currently under budget due to supply chain delays with fleet
purchases. Officers will also continue to seek additional disaster resilience funding opportunities
for the shortfall from State and Federal Government associated with the February 2022 flood
disaster event.
Risks & Opportunities
Finance Risks Mitigation
Budget Overrun Council will engage contractor under schedule of
rates contract and work with contractor to ensure
the project scope remains within budget. Further
project scope increase will be mitigated through
ongoing and stringent monitoring and controls by
the project working group and the Capital Works
Project Control Group and in regular reports to
Page 24 of 35
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.