Decision Notice OPW25 0057 · OPW25/0057
Bioretention Basins – Maintenance & handover
44. Following installation of the filter media for the bioretention devices, a temporary cover
consisting of a suitable geotextile covered with soil and turfed is to be immediately installed.
This temporary cover is to be maintained in place for a minimum period of 24 months
following acceptance of the bioretention devices On Maintenance or until 80% of building
works has been completed (whichever occurs first). Following this period the temporary
cover is to be removed, and the approved plantings installed. The bioretention devices are
then to be appropriately maintained for a minimum period of 12 months prior to being
accepted as Off Maintenance by Council’s delegate.
45. A construction hold point with a council delegate must be established when the temporary
cover is to be removed from the bioretention device an inspection must be arranged with
Council’s delegate
46. Prior to acceptance of the basin either on or off maintenance, council must receive evidence
that the results for the in-situ hydraulic conductivity testing conducted in accordance with
FAWB PRACTICE NOTE 1: In Situ Measurement of Hydraulic Conductivity Belinda Hatt,
Sebastien Le Coustumer April 2008 for the bioretention filter media achieve the design
criteria.
47. Subsoil drains are to be cleaned out and accumulated sediment manually removed from the
surface of basin and coarse sediment forebays at Off Maintenance and as required during
the maintenance period.
48. All stormwater quality treatment devices must be maintained by the development in
accordance with Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version
1) until they are accepted as Off Maintenance by Council.
49. Any defects in WSUD devices identified during the maintenance period must be reviewed
and a report recommending required rectification works submitted to Council and endorsed
by Council’s delegate. Works to repair the device and prevent the problem occurring in the
future must be completed and the device maintained for a minimum period of 12 months prior
to the WSUD device being accepted as Off Maintenance.
50. Prior to council accepting the bioretention devices Off Maintenance, maintenance checklists
including the full cost of maintaining the devices in accordance with Water by Design (2009)
Maintaining Vegetated Stormwater Assets (Version 1) must be submitted to Council.
Erosion and Sediment Control
51. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination. These
measures must be designed, implemented and maintained in accordance with “Best Practice
Erosion and Sediment Control” published by the International Erosion Control Association
(Australasian Chapter) (IECA, 2008), to the extent that such measures and practices are also
consistent with the following:
a. Minimise Erosion:
i. For areas of the site which drain to a sediment basin, implement drainage and
erosion control measures prior to rainfall which prevent or minimise rill erosion
and gully erosion
ii. For areas of the site which do not drain to a sediment basin, implement drainage
and erosion control measures prior to rainfall (including contingency measures)
which prevent or minimise erosion, including rain drop erosion, chemical erosion,
rill erosion and gully erosion
Page 10 of 20
Document Set ID: 24052669
Version: 2, Version Date: 22/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice OPW25 0057.pdfRelated documentApplication case desk ↗
About this file
- File size
- 219 KB (small file)
- File type
No other editions are linked here.