Council archive · source document
Decision Notice OPW25 0057 · OPW25/0057
iii. Prior to the sealing of the plan of survey for the development, all site surfaces
must be effectively stabilised using methods which have achieved effective short-
term stabilisation and which will continue to achieve effective stabilisation in the
medium to long-term. For the purpose of this condition, an effectively stabilised
surface is defined as one that does not, or is not likely to result in visible evidence
of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead
to water contamination.
b. Manage concentrated stormwater flows
iv. Prior to each rainfall event ensure concentrated stormwater flow paths are
provided with capacity in accordance with IECA (2008) Table 4.3.1 and are
structurally stable in all rainfall events for the following sources:
a) From stormwater catchments upslope of the area of disturbance which are
either stable or external to the site, ensure stormwater is diverted or
managed either:
i. around the site or through the site without causing erosion and
without contaminating the flow; or
ii if it is impractical to convey the flows around or through the site,
convey the flows into appropriately sized sediment basins without
causing erosion.
b) From all disturbed areas of the site to sediment basin(s) without causing
erosion
c. Minimise sediment released from the site
i. Prior to each rainfall event ensure concentrated stormwater flow paths are
provided with capacity in accordance with IECA (2008) Table 4.3.1 and are
structurally stable in all rainfall events for the following sources:
a) Each basin is sized and operated in accordance with either a Type-A or
Type-B sediment basin as documented in IECA (2008) Appendix B (June
2018).
b) Each basin is to be provided with an automated system of flocculent dosing
and a suitable supply of flocculent/coagulant, with the type of
flocculent/coagulant determined based on Chemical Coagulants and
Flocculants Fact Sheet (IECA, 2018).
c) Markers are provided within each basin indicating the maximum sediment
storage level and any additional water storage capacity for water reuse.
d) During discharge from the primary outlet system, the concentration of total
suspended solids (“TSS”) discharged does not exceed 50mg/L and that pH
is within the range of 6.5-8.5 unless entering a naturally acidic environment.
ii. Install and maintain additional sediment control measures within the site, as
necessary to maximise sediment capture.
iii. Minimise the tracking of dirt from the site onto roadways. Ensure that all dirt on
roadways caused by vehicles leaving the site is removed without causing water
contamination, prior to rainfall and at least at the end of each work day.
52. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
Page 11 of 20
Document Set ID: 24052669
Version: 2, Version Date: 22/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice OPW25 0057.pdfRelated documentApplication case desk ↗
About this file
- File size
- 219 KB (small file)
- File type
No other editions are linked here.