15. An Arborist Report (or part thereof) prepared by a qualified person* and endorsed
through an Operational Works approval must provide recommendations for the
design of civil works, including retaining walls, to accommodate the retention of the
Mango tree.
16. The Mango tree identified for retention in the conditions of this approval must be
maintained in good health during construction and operational use for the expected
life of the tree.
*(Refer to Advisory Note)
Landscaping Works
17. The development site must be landscaped. The works must be undertaken in
accordance with an Operational Works approval and the Noosa Plan Planning
Scheme Policy PSP 3 – Landscaping Plants and Guidelines and must include in
particular:
a. The works shown on the approved Landscape Concept Plan using
predominately local native species;
b. The provision of 6 x 100L local native street trees to the road frontages suitable
for the location and sight lines.
c. Retention of the mango tree within the north eastern corner of the lot within a
mulched garden setting.
18. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures
healthy, sustained and vigorous plant growth. All plant material must be allowed to
grow to full form and be refurbished when its life expectancy is reached.
19. All landscape works must be maintained generally in accordance with the approved
design for the life of the development.
ENGINEERING
External Works
20. A 2.0m wide concrete footpath must be provided within the road verge for the entire
length of the frontage of the site to Wattle Street. The path must generally match with
the existing grassed verge without causing a trip hazard. The works must be
undertaken in accordance with an Operational Works approval and must
include/address the following:
a. Be in compliance with IPWEAQ standard drawing SEQ R-065 Concrete
Pathway Construction Details;
b. Be extended to smoothly tapered and join with the existing path along Garnet
Street.
Reinstatement Works
21. Any redundant driveway and/or kerb layback must be removed, and the kerb line and
verge area reinstated and landscaped to match the existing kerb and/or verge
treatments. Grassed verge areas to be reinstated must be provided with 100 mm
topsoil and turf, and must be maintained by the developer until established.
Page 5 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.