Operational Works Application OPW20/0148- 20 Mermaid Quay, Noosaville
Very large file: it may take a few minutes
The original of this document is very large (17.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Noosa Council documents
OPW1 7/0170
Plan No. Rev. Plan/Document Name Date
27117-J1 B Jetty Plan and Elevations prepared by 2 June 2017
SCG Consulting Engineers
GAP-D01 Timber Jetty and Drive on Pontoon - 3 May 2017
General Arrangement Plan prepared by
Superior Jetties as annotated by
Council
2. All structures must be designed and constructed such that they are free standing
within the waterway and are not connected to or behind the revetment wall
3. All structures must have no detrimental effects on stormwater drains and/or
easements.
4. Jetties must have a level-walking surface of R.L 1.000 A.H.D or be level with the
top of the revetment wall.
5. A rigid handrail must be fitted on one side of the walkway.
6. No posts or vertical supports of the proposed jetty are to extend vertically from the
structure unless they provide support for the handrail or are required for securing
vessels
7. There must be no electrical reticulation system carrying electricity in excess of 24
volts beyond the revetment wall unless all switches and power outlets are
positioned above the 1%AEP flood level.
8. Lighting associated with the use must be designed, installed, operated, and
maintained in accordance with Section 3 of AS4282 Control of the Obtrusive
Effects of Outdoor Lighting.
9. Rock scour protection, wrapped in geotextile, extends from 750mm up to
approximately 5000mm from the face of the revetment wall in Noosa Waters. Piles
are to be:
a. Located clear of this rock protection where applicable, or alternatively
b. Where the scour protection extends beyond 750mm:
i. Prior to driving piles, the rocks are to be removed to expose the
geotextile and the geotextile cut neatly to allow it to be turned back.
During pile driving, care is to be taken to ensure the geotextile is not
damaged. At the completion of pile driving, the fabric is to be turned
down around the pile and the rocks replaced around the piles
10. The jetty and boat lifting device are to be used for private purposes only with no
commercial operations to be undertaken.
11. Boat repair activities are not permitted on site.
12. Wastewater and sullage must only be disposed of at approved pumpout facilities.
13. The mooring facility must not be utilised for live-aboard purposes.
14. Any construction and post construction activity is not to impact on the condition of
the waterway, and is to be conducted so as not to breach the Environmental
Protection Act EPA (1994) and the Environmental Protection (Water) Policy 2009.
Page 2 of 6
Document Set ID: 20342769
Version: 3, Version Date: 22/06/2017 Print Date: 26 June 2017, 3:18 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.