10. A sealed access driveway must be provided from Landrail Street to the parking and
manoeuvring areas of the development. The works must be generally in accordance with the
approved plan.
11. The proposed access driveway to Oriole Avenue must be construction in accordance with
an Operational Works approval and be generally in accordance with the approved plan and
Council’s Standard drawings RS-049 and RS-050 and any associated addendum.
Stormwater Drainage
12. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge.
Condition 12 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Earthworks
13. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council. All
earthworks must be undertaken in accordance with the provisions of Australian Standard
AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
14. Where the development involves excavation or filling over, or adjacent to, drainage, water
supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
provide a freeboard of 100mm above the finished ground surface level.
Damage to Services and Assets
15. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
DEMOLITION WORKS - CODES OF DEVELOPMENT
16. Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
solutions as contained in the Waste Management Code and Water Quality and Drainage
Code of the Noosa Plan 2020.
Works
17. Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.
Waste Management
18. Adequate area must be provided on-site for the collection and separate storage of recyclable,
non-recyclable, vegetative and hazardous materials in their specific waste streams during
removal or demolition works.
19. All waste materials must be removed from the site to avoid causing unhealthy conditions,
with the site left clean, tidy and free from any debris.
Page 3 of 12
Document Set ID: 24087418
Version: 4, Version Date: 29/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice DBW25 0051 & OPW25 0054.pdfRelated documentApplication case desk ↗
Negotiated Decision Notice DBW25 0051.pdfRelated documentApplication case desk ↗
About this file
- File size
- 200 KB (small file)
- File type
No other editions are linked here.