1810-8094 SRA Response with conditions MCU18-0158
Attached to the e-mail SARA Response with conditions - MCU18/0158.
1810-8094 SRA
worsening or actionable nuisance to the state-controlled road.
(b) at all times
(b) Any works on the land must not:
(c) prior to submitting
(i) create any new discharge points for stormwater runoff onto the Plan of Survey to
the state-controlled road; the local government
(ii) interfere with and/or cause damage to the existing for approval
stormwater drainage on the state-controlled road;
(iii) surcharge any existing culvert or drain on the state-
controlled road;
(iv) reduce the quality of stormwater discharge onto the state-
controlled road .
(c) RPEQ certification must be provided to the North Coast
District Development Assessment team via
[email protected] within the Department of
Transport and Main Roads, confirming that the development
has been designed and constructed in accordance with parts
(a) and (b) of this condition.
6. a) The existing vehicular property access located between Lot 5 (a) and (b) prior to
RP72698 and Cooroy Connection road must be permanently submitting the
closed and removed. Plan of Survey to
the local
(b) The kerb and channelling and the footpath between the pavement government for
edge and the property boundary must be reinstated in accordance approval
with Transport and Main Roads Road Planning and Design Manual
and relevant council standards at no cost to the Department of
Transport and Main Roads’.
Department of State Development, Manufacturing, Infrastructure and Planning Page 5 of 9