they shall be carried out in accordance with Section 3.8 of Council's "Engineering Design
Standards" manual. No earthworks or filling works are to be undertaken until issue of a
Development Permit for Operational Works -Filling.
24. To protect the environment against siltation/sediment export or soil erosion as a result of this
development, an erosion and sediment control plan shall be submitted in conjunction with
any Development Permit for Operational Works. Site control measures such as silt fencing,
controlled gravel access to the site and controlled disposal of waste, may be necessary. Prior
to commencement of Operational Works and/or Building Works, all physical site control
measures shall be installed, and the plan adhered to.
Prior to commencement of Operational Works a $2,000 site control bond is required to be
lodged with the Council to ensure compliance with this condition.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
this condition or any additional inspections incurred for substandard work or works
undertaken not in accordance with this permit.Land Use
25. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan Name Date
DA.01 4 Site Plan (as annotated), drawn by Thomson 23.08.2017
Adsett
DA.02 2 Demolition Plan, drawn by Thomson Adsett 15.08.2017
DA.03 3 Proposed floor plan (as annotated), drawn 23.08.2017
by Thomson Adsett
17BRT0143 D Sheet 1 of 3 Recommended traffic modifications – site 29.11.2017
plan, (as annotated) drawn by TTM
Consulting Pty Ltd
17BRT0143.02 D Sheet 2 of 3 Recommended traffic modifications – 29.11.2017
northern area, drawn by TTM Consulting Pty
Ltd
17BRT0143.02 D Sheet 3 of 3 Recommended traffic modifications – 29.11.2017
southern area (as annotated), drawn by TTM
Consulting Pty Ltd
17BRT0143.03 A Sheet 1 of 1 Recommended traffic modifications – 29.11.2017
Southern area – B99 vehicle sweep paths,
drawn by TTM Consulting Pty Ltd
26. The total use area of the development is 4,568m2
27. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
28. The colour scheme for the development is to be generally in accordance with the approved
plans.
29. The open space and setback areas are to be landscaped in accordance with Council’s Policy
on Landscaping Guidelines and a properly prepared landscape plan. Such landscaping is
to be completed prior to the premises being occupied and maintained at all times thereafter
to the reasonable satisfaction of the Manager Land Use.
The road reserve to the frontage of Gibson Road, is to make provision for dense trees and
shrubs that will assist in screening the development from the view of Gibson Road. This is
to include trees and shrubs of a minimum of 100 litre pot size. Furthermore, additional
Page 4 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachement D - Minor Change Approval.pdfRelated documentApplication case desk ↗
About this file
- File size
- 539 KB (small file)
- File type
No other editions are linked here.