4.8.4 Continue implementation of the Coastal Hazards Strategy and Living Foreshores Noosaville (linked to Noosaville Foreshore Infrastructure Master Plan)
Adaptation Plan, including planning for Living Foreshores Sustainability has minor timeline disruptions due to community consultation Round 2. Living Foreshores
Noosa, Coastal Wetland Restoration Project. Hilton Esplanade has minor timeline disruptions due to significant increase in consultancy
market rates that are being worked through with QCoast. Coastal Wetland Restoration
Project Phase 1 (Blue Carbon) complete with final report received in June 2024.
Note-relisted in the new 24/25 Operational Plan
4.8.5 Advance flood resilience projects including updating the Strategy and Flood Management Operational Plan in final draft. Noosa River Flood Study and Six Mile
Noosa River Flood Study, Six Mile Creek Flood Study and Sustainability Creek Flood Study updates are on track with ITQ now closed and tender evaluation and
Noosa Flood Management Operational Plan. award to be completed within Q1. Estimated completion June 2025.
Note-relisted in the new 24/25 Operational Plan
4.9 Commence development of a program for long term Corporate Initial pipeline of work being developed as part of the Long-Term Financial Plan.
implementation of contemporary revenue diversification Services Note-relisted in the new 24/25 Operational Plan
and a strategic investment approach that identifies Director
innovative and alternate revenue streams for council.