ANNUAL PERFORMANCE REPORT INCLUDING Q4 OPERATIONAL PLAN 2023-24 PROGRESS REPORT · Attachment 1 - Annual Progress Report to 30 June 2024, incorporating the Q4 progress Report (1 April to 30 June 2024)
Plans and drawings: the text below has words only, no drawings.
On Track Initiatives
OP Initiative Service/Mgr Status Reason for Status
Ref Responsible
5.1.1 Develop and commence implementation of a Customer Community Draft Customer Experience Program developed. Implementation dependant on
Experience Program. Services resourcing availability.
Director Note-relisted in the new 24/25 Operational Plan
5.1.2 Investigate options for expanding Council Customer Community Trial Customer Service desk at Cooroy Library underway - due for review in Nov 2024.
Service operations beyond Tewantin administration Services Note-relisted in the new 24/25 Operational Plan.
building. Director
5.4.5 Prepare for and commence the negotiation process to People & Preparations undertaken including representatives on the Bargaining Team and
negotiate Council’s new certified Agreement. Culture identification of workplace issues. Negotiations to commence in September 2024.
Note-relisted in the new 24/25 Operational Plan
5.5.2 Implement actions to increase the effectiveness of the Executive Progress to action recommendations from the review of the effectiveness of the Audit and
Audit and Risk Committee and the internal audit function. Officer Internal Risk Committee and internal audit model underway with the involvement of the ARC.
Audit & Note-relisted in the new 24/25 Operational Plan
Corporate
Performance
Disrupted Initiatives
OP Initiative Service/Mgr Status Reason for Status
Ref Responsible
5.1.3 Assess the community’s satisfaction with Council services Community Delayed to 2024/25 pending resource availability.
and Liveability score. Services Note-relisted in the new 24/25 Operational Plan.
Director / CEO
5.2.1 Identify efficiencies in Council Utilities incl (water, Corporate Utilities Analyst engaged and commencing 2-year analysis, review and implementation
sewerage, electricity, gas) to ensure cost effective and Services program.
efficient services in line with sustainability principles. Director Note-relisted in the new 24/25 Operational Plan
5.2.3 Develop Council's Performance Measurement Framework. Executive The development of the Framework is progressing. A review of service profiles including
Officer Internal the identification of efficiency and effectiveness measures was undertaken with the
Audit & Service Catalogue included in the 24-25 Budget adoption process. Corporate Plan
Corporate performance measures/data being refined in preparation for reporting to Council.
Performance Note-relisted in the new 24/25 Operational Plan
5.2.5 Finalise the Contract Management Framework and develop Procurement Contract Management Framework & suite of documents has been finalised.
an implementation plan. Implementation Plan to be finalised in Q1 24/25.
Note-continuing, to be included in new 24/25 Operational Plan.
5.3.1 Develop a new ICT and Digital Strategy to provide the Corporate New ICT Management leading development of new ICT and Digital Strategy. Baseline
foundation for technology requirements and digital Services assessment complete.
transformation over the next 5 years. Director Note-relisted in the new 24/25 Operational Plan