Appendix D - Engineering Assessment · OPW26/0090
An aerial image of the site is shown in Figure 1. For further detail of the existing site, refer to the detailed
survey plan prepared by Surveyors Co dated 08 May 2025.
Figure 1 Subject Site Aerial (Source: Noosa Intramaps)
Flooding
The subject site is not flagged by Council’s Flood Hazard Overlay Map. No recommendations are provided.
Stormwater Quantity
A Rational Method hydrologic model in accordance with the Queensland Urban Drainage Manual (QUDM)
was developed to quantify the stormwater discharge for the major and minor storm event. The following
parameters were used for the model:
- Storm event recurrence intervals were selected in accordance with QUDM Tables 7.3.1 and 7.3.2:
o Minor event: 0.5 EY
o Major event: 1% AEP
- Intensity, Frequency, and Duration rainfall data was sourced from the Bureau of Meteorology’s
2016 dataset. Intensities were multiplied by 1.15* to estimate present-day intensities due to
Climate Change.
- Catchment coefficients and areas were obtained by comparing the detailed survey against QUDM
Table 4.5.3
- Time of Concentration was taken as the standard inlet time of 5 minutes (QUDM Section 4.6.4)
- In the ultimate post-development scenario, it is assumed that Lot 1 will be developed to
approximately 75% impervious, and Lot 2 will remain as-is.
www.sunshinecoastcivilengineers.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix D - Engineering Assessment.pdfRelated documentApplication case desk ↗
Appendix D - Engineering Assessment.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.