OPERATIONAL PLAN 2018-19 PROGRESS REPORT
LONG TERM PLANNING FOR NOOSA SHIRE
No. Project Responsibility Update Status
1 Complete State interest review and community Director Environment & Sustainable State Agency Interest Review complete, now awaiting Minister sign off for On track @
consultation for draft new Noosa Planning Scheme Development community consultation to begin.
2 Progress remaining matters associated with the Property Manager The primary action plan for the Foreshore Plan comprised the 10 items in On track o
Noosaville Foreshore Land Use Master Plan Council's resolution. All have been actioned, and those requiring
ownership/action by other Departments (Items E, F, G & H) have been
discussed with those Departments to progress.
3 Implementation of Noosa Transport Strategy priority Director Infrastructure Services Christmas period transport trials underway. Additional trial data being On track @
actions collected for future evaluation and reporting to Council.
4 Commence the Noosa North Shore Campground Property Manager Tender closed December 2018. Currently under evaluation by tender review On track oO
redevelopment panel.
5 Complete detailed Asset Management Plans Asset Planning Manager Council adopted the Road Infrastructure Asset Management Plan at the Behind Schedule O
December 2018 Council meeting. Ongoing development of the Stormwater
and Buildings and Facilities Asset Management Plans are to be rolled out
throughout the remainder of the year. Data reconciliation has increased the
time frame for the delivery of the remaining Asset Management Plans, with
the Stormwater Asset Management Plan to be presented to Council in
February 2019.
6 Finalise Climate Change Adaptation Plan and initiate Director Environment & Sustainable Updated modeling (i.e. additional scenarios) sought by Council and supported On track @
implementation of actions Development by State Government, with the completion of this task expected by end
January 2019. Work on risk analysis and adaptation measures progressing
well, completion expected end of February 2019. Submission of Coastal
Hazard Adapation Plan to State still expected by end 2018/2018 Financial
Year. The Climate Change Adaption Plan is progressing as per updated
project schedule.
Page 113 of 130See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.