               5.     No part of the building extension shall exceed a height of 9m to the peak or ridge of any
                      pitched roof, and 8m elsewhere above the natural ground level and the finished ground level.
                      Except for the peak of the approved annexe building which must not exceed a height of
                      9.05m above the natural ground level and the finished ground level.
               6.     Any advertising sign or device is to comply with Council's policies on advertising.
               7.     Security in the form of a cash bond or trading bank guarantee to the sum of $5000 must be
                      submitted, to secure performance of all conditions of this approval, prior to the issue of a
                      Development Permit for operational works. The cash bond or trading bank guarantee will
                      be returned on performance of the conditions of approval less any costs incurred by Council
                      in respect of enforcing performance of this permit.
               8.     The requirements of this development approval are to be effected, prior to the use of the
                      premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
                      this approval to effect compliance with conditions.
               9.     The developer must obtain all of the other Development Permits referred to in the Decision
                      Notice, prior to obtaining a Development Permit for Building Works.
               10.    The maximum number of people to be accommodated on site is 52, which includes all
                      teaching, caretaking and other staff.
               11.    The proposed development shall have all bathroom fittings comply with the AAA Water
                      Conservation Rating System as defined by the AS/NZS 6400 (Water Efficient Products -
                      Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and Drainage Standard
                      Part 1.2), with toilets to comply with the AAAA Water Conservation Rating System. All tap
                      ware and shower roses shall not exceed a maximum flow of 9 litres per min.
               12.    All additional hot water systems shall be either solar systems; electric heat pump systems;
                      or gas systems (LPG or natural).
               13.    This Development Permit for a material change of use of premises lapses if:-
                      13.1. the use or erection of a building or other structure associated with the use, has not
                            happened by 19 May 2009, unless application is made and approved by Council for an
                            extension; or
                      13.2. the use of the premises (extension to educational establishment) pursuant to the
                            Development Permit ceases.
               Land Development
               Carparking Off Street
               14.    The new carparking shall be provided within the site as shown on Dhamma Rasmi – Master
                      Plan prepared by Bal Salrai LFRAIA Architect and referenced as Number 15 – Staff
                      Carparking, except as modified herein.
               15.    A minimum of 25 uncovered carpark spaces shall be provided on site, which shall include
                      the existing 20 spaces and the proposed new 5 spaces. The proposed new 5 spaces shall
                      include 1 clearly defined disabled carpark space.
               16.    The proposed new car parking area outside Reception Office shall be designed to comply
                      with the provision of AS2890.1-2004 for user class 1 with allowance for vehicles to enter and
                      leave the site in a forward gear.
               17.    The proposed new car parking area outside the Reception Office shall be kept, maintained
                      in a condition fit for use.
               18.    The new carparking area shall be free draining and the pavement constructed to a gravel
                      access road standard. Plans and specifications for these works shall be submitted in
                      conjunction with an application for a Development Permit for Operational Works.
               Pathways
               19.    Deleted.


                                                                                                       Page 3 of 7
Document Set ID: 21091411
Version: 5, Version Date: 21/02/2020
Log in to download the original file

Attachment B -Minor Change approval.pdf · 6.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.