Attachment B -Minor Change approval

of 19

Page text shows just the words. Original shows the document exactly as it was published.

Original PDF page 4, section 1. The text section number identifies this passage in the reader.

               Vegetation Protection
               20.    Additional pavements within the drip zone of any of the existing trees on site to be retained
                      shall be designed as a pervious pavement (such as grass paving cells or similar), as this will
                      allow water that falls on this surface to penetrate to the trees root system. The pavement
                      shall be constructed so as not to damage the tree or their root system and in this regard
                      temporary fencing shall be provided around the trees during construction to help protect
                      them.
                      Plans shall be submitted to the Council for approval that clearly show the type and extent of
                      the pervious pavement and the temporary fencing prior to obtaining a Development Permit
                      for Operational Works.
               Stormwater Drainage
               21.    All stormwater drainage shall be collected on site and discharged so there is no net increase
                      in stormwater runoff from the site.
               22.    All site stormwater drainage from the additional structures shall be by means of a gravity
                      system.
               23.    Roof runoff shall be directed to a rainwater storage system or tank (minimum storage 1000
                      litres) that is plumbed to service the toilets and bathroom of each new cabin. The design of
                      the rainwater storage system shall be to the satisfaction of the Manager Plumbing Services.
               24.    To ensure that polluted run-off does not enter the tributary of Cooroora Creek, stormwater
                      run-off from the new carparking area and any new driveways shall have the first flush (the
                      first 12 mm of rainfall or hose-down) treated via a grassed swale or similar treatment system
                      using Water Sensitive Urban Design principles.
               Effluent Disposal
               25.    Deleted.
               Earthworks
               26.    Filling works required on site shall be carried out in accordance with Section 3.8 of Council’s
                      Engineering Design Standards Manual and so as not to cause the ponding of water on any
                      adjoining lands or the blockage of, or interference with, any natural watercourses.
               27.    Deleted.
               Erosion and Sediment Control
               28.    Any person acting on this permit shall prevent erosion and sediment export from leaving the
                      site. Site control measures such as silt fencing, controlled gravel access to the site and
                      controlled disposal of waste, will be necessary.
                      In this regard plans detailing the methods of controlling erosion and sediment are required
                      to be submitted to the Council for approval prior to obtaining a Development Permit for
                      Operational Works.
               General
               29.    Any damage caused to any public utility during the course of construction shall be repaired
                      to Council’s standards and at no cost to Council.
               30.    The transportation of all materials to and from the site shall be undertaken in a manner such
                      that no particle matter escapes onto a public road. All vehicles carrying materials either to
                      or from the site shall be covered to prevent materials including dust being windblown from
                      the vehicle.
               Environmental Health
               31.    Deleted.
               32.    Deleted.



                                                                                                        Page 4 of 7
Document Set ID: 21091411
Version: 5, Version Date: 21/02/2020
Log in to download the original file

Attachment B -Minor Change approval.pdf · 6.2 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.