Operational Works Report_RosesRd Access 29 April2025
Callaghan & Toth
4.2.2 Earthworks Code
The works generally comply with the Earthworks code, as detailed below in Table 6.
Table 6: Response to Table 9.4.2.3 - Earthworks
Performance outcomes Acceptable Outcomes RESPONSE - Earthworks
Code
Assessable Development
Effects of works
Drainage AO1 Complies with PO1
PO1 Filled or excavated areas have a
The driveway design ensures that
Finished surface levels ensure minimum gradient of 0.5% and drain
the site is free draining and drains
land is free draining. to Council’s stormwater infrastructure
to Skyring Creek as per current
where available, or where
flow paths on site.
stormwater infrastructure is not
available, toward the street.
Hydraulics
Complies with PO2
PO2
Change to the levels on site do No acceptable outcome provided The proposed driveway and
not have an adverse impact on associated drainage works e.g.
the flooding and drainage table drains, culverts under
characteristics off-site. driveway, do not change existing
flooding or drainage characteristics
on the site and adjacent areas.
Geotechnical considerations AO3.1
Complies with PO3
PO3 Filling works are undertaken in
Earthworks do not result in accordance with Council’s Planning
geotechnical instability on-site or Scheme Policy PSP6 Engineering
The works are not adjacent to
to nearby premises. design standards - roads, drainage
dwellings or buildings
and earthworks.
AO3.2
Where the filling is for residential,
commercial or industrial purposes
the works comply with Australian
Standard - Guidelines for earthworks
on commercial & residential
development.
Local amenity AO4.1
Complies with PO4
PO4 The following control measures are
Undertaking earthworks does not implemented—
adversely impact on the amenity regular water spraying of exposed The works will not cause any major
of the local area by way of dust, areas to suppress dust; impact to dust or noise. The works
noise or visual amenity. 1. provision of dust stabilised or are expected to take 4 months and
sealed internal roads; will be managed to reduce dust
2. protective covering of exposed and noise emissions.
areas that are left for more than
2 weeks; and
3. unless a development permit
provides otherwise, disturbed
areas are revegetated using
species identified in Council's
Planning Scheme Policy PSP2
Landscaping.
AO4.2
Earthworks are undertaken only
Operational Works Application – Supporting Information April 2025
36 Roses Road, Federal 10