Building Height
4. The maximum height of the development must not exceed 8 metres above the ground level.
Boundary Wall
5. The total length of all buildings or parts, of any class within the western boundary setback
must not exceed 9 metres in length and have a mean height* of not more than 3.5m
*(Refer to Advisory Note)
External Colours & Finishes
6. External colours and finishes must be of muted environmental tones that blend with the
surrounding vegetation and landscape, with broad expanses of a single colour or reflective
surfaces not permitted.
Protection of Privacy
7. To ensure privacy is protected between adjoining properties, the windows located on the
upper level western wall to the master suite, retreat and office of the dwelling must either:
a. have a minimum window sill height or 1.75 metres above floor level; or
b. be fitted with translucent glazing; or
c. be fitted with a fixed external screen.
Car Parking
8. A minimum of 2 covered car parking spaces must be provided on site and made available
and accessible at all times for residents.
Lighting Amenity
9. No flood lighting must be used on site. Any vertical illumination resulting from direct, reflected
or other incidental external lighting emanating from the site must not exceed 8 lux when
measured at any point 1.5 metres outside the boundary and at any level from ground level
upward.
Environment
10. Sediment or any other material including building materials or waste products must not be
deposited or released into the road reserve, stormwater drain or adjacent properties.
Stormwater Drainage
11. Stormwater runoff from the development must be discharged to Mermaid Quay without
causing scour or damage to the subject site or any adjoining property.
Damage to Services and Assets
12. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Bonds
13. A site compliance bond of $5,000 is to be submitted to Council prior to the commencement
of works. The commencement of works can only commence once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
Page 3 of 7
Document Set ID: 22652133
Version: 2, Version Date: 07/11/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - DBW23 0044 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 247 KB (small file)
- File type
No other editions are linked here.