Original source · versioned page text
Further Council Report MCU21-0110.pdf
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 11 JUNE 2024
17. The development must incorporate the colour scheme and proposed mix of building
materials as outlined in the approved plans.
18. Any security screens on the premises consist of grille or translucent screens and not
solid shutters, screens or roller-doors.
19. All mechanical equipment and other service infrastructure located on the site must be:
a. located not less than 2 metres from a property boundary;
b. fully enclosed or screened such that they are not visible from the street frontages
nor adjoining properties. Where screened by landscaping, landscaping beds must
be at least 1.5 metres wide.
20. No part of the site may be used for outdoor storage of materials.
Performance Bond
21. Security in the form of a cash bond or trading bank guarantee to the sum of $200,000
must be submitted to Council, to secure performance of all conditions of this approval,
prior to pre-start meeting. The cash bond or trading bank guarantee will be returned on
performance of the conditions of approval less any costs incurred by Council in respect
1
of enforcing performance of this permit. Council reserves the right to call upon the bond
or guaranteed sum to effect compliance with conditions.
T
Tennis Court Fencing
EN
22. Tennis court fencing must be comprised of black powder coated posts and rails with
black PVC coated chain wire mesh, or the like.
Tennis Court Light Spillage and Glare
M
23. Lighting must be directed onto the site and away from neighbouring properties.
24. The level of light emanating outside the property must not exceed an illumination level
H
of 12 lux nor an average of 10 lux when measured 3 metres outside the property
boundary.
C
25. The light fittings must be baffled to ensure that a light source is not directly visible from
TA
the habitable room window of an adjoining property.
26. All light readings are to be taken in a horizontal plane at a height of 1000mm above
ground level.
AT
Tennis Court Operating Hours
27. Tennis courts must not be illuminated after 10.00p.m. nor before 7.30 a.m.
Structural Stability
28. All lighting support columns must be manufactured from galvanised steel.
29. The pole height shall not exceed 8 metres.
30. The pole and associated concrete footing design must be engineer certified to support
the light fitting and to withstand wind loads appropriate to the terrain classification.
Tennis Ball Machines
31. Machines which operate on the air compression principle must not be used after 7.00
p.m. nor before 8.00 a.m.
32. Silent running machines which operate at a noise level not exceeding 10 decibels
(when measured at the property boundary) must not be used after 10.00 p.m. nor
before 7.30 a.m.
Page 4 of 12
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Further Council Report MCU21-0110.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.