MCU14/0073 - Decision Notice - 1036841

of 14

Text shows just the words. Original shows the document exactly as it was published.

                                                                                                            SDA-0914-014464




                              b.       20 visitor/customer parking spaces within the total, which are clearly marked
                                       for that purpose and accessible at all times for visitor/customer use
                              c.       2 disabled parking space/s within the total
                              d.       a sealed surface with crossfalls and gradients in accordance with Australian
                                       Standard AS2890: Parking Facilities
                      13.     Directional signage must be provided to direct visitors and customers to the car
                              parking spaces provided on site.
                      Bicycle Parking & End of Trip Facilities
                      14.     Bicycle facilities in accordance with AS2890.3 Bicycle Parking Facilities must be
                              provided for the development. The facilities must be indicated on the plans and
                              submitted in accordance with an Operational Works approval and must include in
                              particular:
                              a.       a total of 10 bicycle parking spaces
                              b.       end of trip facilities involving a minimum of 5 lockers and 1 shower cubicle
                                       with an ancillary change room.
                      Damage to Services and Assets
                      15.     Any damage caused to existing services and assets as a result of the development
                              works must be repaired at no cost to the asset owner at the following times:
                              a.       where the damage would cause a hazard to pedestrian or vehicle safety,
                                       immediately; or
                              b.       where otherwise, upon completion of the works associated with the
                                       development.
                              c.       Any repair work which proposes to alter the alignment or level of existing
                                       services and assets must first be referred to the relevant service authority for
                                       approval.
                      Stormwater Drainage
                      16.     The site must be provided with a stormwater drainage system connecting to a
                              lawful point of discharge. The works must be undertaken in accordance with an
                              Operational Works approval, the Queensland Urban Drainage Manual and
                              Engineering report dated 3 September 2013 by Barlow Shelly Consulting
                              Engineers (with the works expanded to reflect the extended development area).
                      Stormwater Quality Management
                      17.     A stormwater quality treatment system must be provided for the development. The
                              works must be undertaken in accordance with an Operational Works approval and
                              must include in particular:
                              a.       stormwater quality treatment devices of a size and location generally in
                                       accordance with those shown in section 5.0 and 6.0 of the of the Engineering
                                       report dated 3 September 2013 by Barlow Shelly Consulting Engineers (with
                                       the works expanded to reflect the extended development area)
                              b.       swales which are designed in accordance with the Water Sensitive Urban
                                       Design Technical Design Guidelines for South East Queensland
                              c.       The works must be undertaken in accordance with the Bioretention Technical
                                       Design Guidelines (Water by Design, 2012)




                     Department of State Development, Infrastructure and Planning                             Page 4
Document Set ID: 19845988
Version: 1, Version Date: 22/12/2014

Used in these records

About this file

File size
297 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

MCU14_0073 - Decision Notice - 1036841.pdf · 297 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.