NOOSA COUNCIL IDAS Development Application Decision Notice                                                    6 of 11


37.    For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development shall be
       served by:

       37.1. A single Body Corporate water meter to measure the total water consumption (including fire hose
             reels, but excluding fire hydrants and fire sprinkler systems), and

       37.2. Individual water meters to each tenement capable of being separately rated, and

       37.3. A fire service (fully testable single detector check with metered bypass), where applicable, for flows
             to fire hydrants and fire sprinkler systems (excluding fire hose reels).
Earthworks
38.    Earthworks works required on site shall be carried out in accordance with Section 3.8 of Council’s
       Engineering Design Standards Manual and so as not to cause the additional ponding of water on any
       adjoining lands or the blockage of, or interference with, any natural watercourses.

39.    Earthworks carried out on site shall not affect the structural integrity of any of the existing fences or
       structures that border the development site. Fences that are affected shall be replaced prior to the
       Building Certifier issuing the Certificate of Classification. In this regard any fences to be replaced shall be
       clearly shown on the plans submitted for Operational Works approval.
Erosion and Sediment Control
40.    Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
       control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
       waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
      to the Council for approval prior to obtaining a Development Permit for Operational Works.
Contributions Towards Council Infrastructure
41.    Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or upgrading
       various infrastructure at the rates applicable at the time of payment. An estimate only of the contribution
       amounts under the current Council policies and requirements is outlined in the table below:

          Contribution Required For:                                                             Amount:

          PSP12 – Public Open Space Contributions (Park)                                         $2,667
          PSP16 – Sewerage Headworks Contributions                                               $2,434
          PSP17 – Water Supply Headworks Contributions                                           $3,617
          PSP20 – Pathway Trunk Network Contributions                                            $1,918
          TOTAL Contribution Amount =                                                            $ 10,636
          Please note, that these amounts are all subject to variations in the Consumer Price Index, All Groups Brisbane
          from March 2007 until the date of payment.

       All contributions must be paid prior to the issue of a Development Permit for Operational Works.
       Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the contributions
       not be paid at the due time, Council shall call upon the trading bank guarantee in full.
       Processing of bonds for security where specific Council approval has been given for the bonding of
       contributions will incur an administration fee in accordance with Council’s Land Development Commercial
       & Regulatory Fees at the time of lodgement.
       In the event that the Development Permit for Material Change of Use of Premises lapses or is cancelled,
       the trading bank guarantee will be returned.

General
42.    A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
       specifications for all engineering works which shall be submitted in conjunction with an application for a
       Development Permit for Operational Works.

43.    Digital detailed designs including drawings, calculations, etc, shall be submitted with any application for a
       Development Permit for Operational Works in respect of roadworks and stormwater drainage works. The
       design shall be in accordance with Council’s Planning Scheme Policy PSP05 – Engineering Design
       Standards – Roads, Drainage and Earthworks. To avoid conflict with underground pipes or services, all
       existing and proposed services required by the development shall be shown on the plans.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@a401d4bc\@[email protected]

Used in these records

About this file

File size
54 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

00157ADA.001.pdf · 54 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.