NOOSA COUNCIL IDAS Development Application Decision Notice 7 of 11
44. Any damage caused to any public utility during the course of construction shall be repaired to Council’s
standards and at no cost to Council.
45. Any alteration of any public utility or other facilities necessitated by the development of the land or
associated construction works external to the site shall be at no cost to Council.
46. The transportation of all materials to and from the site shall be undertaken in a manner such that no
particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall
be covered to prevent materials including dust being windblown from the vehicle.
Environmental Health
47. Where the development involves the removal, relocation or demolition of a building, a Waste
Management Plan (construction and demolition) shall be submitted prior to demolition, removal or
relocation of any building other than a shed.
Waste Management Plans (construction and demolition) are required to be submitted in accordance with
Planning Scheme Policy 11, Waste Management Plans see table below.
Waste storage areas are to provide for adequate separation of all reusable, recyclable and waste
materials. These shall be located so that they are convenient and safe to use. (Refer to Noosa Council
Waste Management Code)
The Plan shall contain the following information:
The site area for the storage and separation of waste is to be shown on the plan drawings
accompanying the application.
A waste management table as indicated below is to be completed showing how waste material is
to be segregated - recycled – reused or disposed.
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected waste Estimated On-site Off-site *specify contractor
materials volume(m³) *specify proposed *specify contractor and landfill site or
re-use or on-site and recycling outlet other disposal site
recycling methods
Excavation material
Green waste
Bricks
Concrete
Timber-please
specify
Plasterboard
Metals - please
specify
Asbestos
Other - please
specify
Note * If a demolition contractor is undertaking works, then the Waste Management table is to be
completed by the demolition contractor.
The purpose of the Waste Management Plan is to facilitate the segregation of waste for the effective reuse
and recycling of such materials. Additionally Council rewards those who segregate waste by significantly
reducing disposal fees at the landfill some items are free. Higher gate fees are charged for loads of mixed
waste.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@a401d4bc\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
00157ADA.001.pdfRelated documentPublic source context ↗
Decision Notice - 010.2007.00000643.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 54 KB (small file)
- File type
No other editions are linked here.