SDA-0117-036529 - s285 Concurrence agency response With conditions_combined
Attached to the e-mail Concurrence agency response with conditions - Claude Batten Dr.
SDA-0117-036529
No. Conditions Condition timing
14. Until the works have been completed, permit access to the place For the duration of
where the works are located by Department of Agriculture and the works the subject
Fisheries officers if requested. of this approval
15. Mark with buoys the boundary of the approved tidal component Prior to the
of the development footprint, as shown on the following plans: commencement of
o Site 1, prepared by International Coastal the works, and to be
Management, dated 20 Oct 2016, reference maintained until the
works have been
2016.0028-004, revision A;
completed
o Site 2, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-005, revision A;
o Site 3, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-006, revision A;
o Site 4, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-007, revision A;
o Site 5, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-008, revision A;
o Site 6, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-009, revision A;
o Site 7, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-010, revision A;
o Site 8, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-011, revision A;
o Site 9, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-012, revision A;
o Site 10, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-013, revision A;
o Site 11, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-014, revision A;
o Site 12, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-015, revision A;
o Site 13, prepared by International Coastal
Management, dated 20 Oct 2016, reference
2016.0028-016, revision B;
o Site 14, prepared by International Coastal
Management, dated 20 Oct 2016, reference
Department of Infrastructure, Local Government and Planning Page 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.