GENERAL COMMITTEE MEETING AGENDA                                                14 JANUARY 2019


Time risks
   Wet weather delays. The timing for construction mitigates these risks by working during the
     typically drier months of the year with works planned to commence post summer season.

Environmental risks
    Proximity of works to the Coastal Management District. Council staff have liaised and
      confirmed with the Departments of Environment and Science, and State Development,
      Manufacturing, Infrastructure and Planning, that these works are exempt from the
      development processes, as it is operational in nature.
    Proximity to turtle breeding habitats. The street lighting design was developed by Energex’s
      Public Lighting department to minimise light pollution impact on the beach dunes, a known
      turtle breeding site. The streetlights have been installed prior to these civil works to reduce
      the risk of concurrent delays to Council.

Safety risks
   Exceed will be appointed as the Principal Contractor and responsible for the Workplace
     Health and Safety (WHS) of the construction site. Prior to construction commencing, WHS,
     traffic and pedestrian management plans are required to be submitted to Council for
     approval. Council will undertake regular audits on contractor compliance with these approved
     plans throughout construction.

Scope & Quality risks
   Exceed are a prequalified supplier to both Noosa Shire and Sunshine Coast Regional
     Councils through the SA161 Construction of Concrete Pathways supplier arrangement panel.
   The risk of meeting project objectives will be managed via Council staff reviews.

Resourcing risks & opportunities
  Exceed have demonstrated resourcing and capability on similar works for Council previously,
    including re-establishing and completing the installation of precast islands after asphalt
    surfacing by Council’s contractors.
  Coordinated works. By coordinating these civil works in conjunction with the annual
    resurfacing program, construction efficiencies can be obtained by Council and is the best
    approach to minimising the disruption to the travelling public.

Consultation
External Consultation - Community & Stakeholder
Consultation for this project has been undertaken through an extensive public community
engagement process, including using the Your Say Noosa web portal. There was overwhelming
public support for the implementation of the proposed safety improvements.

Internal Consultation
Corporate Services (Financial Services, Procurement)
Infrastructure Services
Environmental & Sustainable Development (Environmental Services)




                                                                                      Page 25 of 40
Log in to download the original file

2019-01-14 General Committee Meeting Agenda(PDF, 2MB).pdf · 2.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.