PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 19 AUGUST 2014
2 APPLICATION FOR MATERIAL CHANGE OF USE - SERVICE AND UTILITY TYPE 3
(TOWER) SITUATED AT GRAHAMS RD, PINBARREN
DOCUMENT IN FOR MATI ON
Author Development Planner, Jack Lewis
Planning & Infrastructure Department
Index ECM/ Application/ MCU13/0067
Attachments 1. Response by Applicant
2. Indicative Coverage Map
RECOMMENDATION
That Council note the report by the Development Planner to the Planning & Organisation
Committee Meeting dated 19 August 2014 regarding Application No. MCU13/0067 for a
Development Permit for Material Change of Use for Service & Utility Type 3 Tower situated at
Grahams Road, Pinbarren; and
A. Approve the application in accordance with the following conditions:
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of the Decision Notice must be complied with
prior to the use commencing, and then compliance maintained at all times while the
use continues.
Approved Plans
2. Development authorised by this approval must be undertaken generally in
accordance with the Approved Plans listed below, unless otherwise amended by the
conditions of approval.
Plan No. Rev. Plan Name Date
4POM-51-09-COTT-C2 04 Overall Site Plan drawn by Aurecon 15/04/2014
4POM-51-09-COTT-C3 04 Site Set out Plan drawn by Aurecon 15/04/2014
4POM-51-09-COTT-C4 04 Site Elevation and Details drawn by 15/04/2014
Aurecon
Building Height
3. The maximum height of the structure must not exceed 31 metres above the finished
ground level and the natural ground surface.
4. Certification must be submitted to Council from a Licensed Surveyor which certifies
that the monopole structure does not exceed the maximum height requirement of this
Decision Notice.
5. No lights are permitted to be attached to the telecommunications facility, except
where required for aircraft hazard lighting purposes or similar.
Page 7 of 155
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.