Delegated Report - Code - Planning MCU23 0038 [As Published] · MCU23/0038
DEVELOPMENT ASSESSMENT DELEGATED REPORT
Author Planning Consultant
Development Assessment
APPLICATION DETAILS
Application No. MCU23/0038
Applicant Provectus Algae
Proposal Material Change of Use - Aquaculture
Properly Made Date 12 April 2023
Information Request Date Not Applicable
Information Response Date Not Applicable
Decision Due Date 4 October 2023
Report Reviewed & Tara Norley - 15 September 2023
Finalised By
PROPERTY DETAILS
Property Address 14-16 Action St Noosaville
RP Description Lot 290 MCH 811938
Land Area 6785m²
Existing Use of Land Industrial shed
STATUTORY DETAILS
SEQRP Designation Urban Footprint
Zone Medium Impact Industry
Precinct Not Applicable
Local Plan Area Noosaville
Overlays Acid Sulfate Soils
• Above 5m AHD to 20m AHD
Assessment Type Code
Document Set ID: 22408646
Version: 6, Version Date: 15/09/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 7 pages
Page 2
1. PROPOSAL
The application seeks approval to operate an aquaculture facility within an existing industrial shed
(being approximately 1,112m2 in area) and two additional structures (equating to approximately
380m2 located along the western boundary) at 14-16 Action Street, Noosaville. The no changes
are proposed externally to the existing industrial building, with the two additional structures having
been places on site between June and November 2022.
The proposed facility is intended to culture marine and freshwater microalgae species in closed
system bioreactors and will operate in association with the existing research and technology
industry. The bioreactors are contained within fully enclosed workrooms on the site. Once fully
operational, the applicant advises this facility is proposed to be equipped with 45 separate
bioreactors, capable of containing 180,000 litres. The bioreactors will be housed in a securely
enclosed building with restricted entry. To minimise water consumption and waste water
generation, a recirculating system is proposed.
The applicant’s Environmental Management Plan submitted to the SARA includes a detailed
description of the proposed operations with the pertinent issues included/summarised below:
Water Management
The recirculating production system is designed to ensure the efficient utilisation of water resources
throughout the entire production process. Water is carefully managed, filtered and recycled within
the closed system, minimising the need for additional water inputs and reducing overall water
consumption. Furthermore, the design of cleaning and washdown procedures takes into account
the objective of minimising water consumption.
Certain species intended for production grow in saline environments. Salt water utilised in
production will exclusively originate from operators who possess a valid water collection permit.
External auditing and certification mitigates the risk of unacceptable ecological impacts. Permit
currency shall be audited in accordance with the Annual Audit Schedule.
Wastewater Management
The recirculated algae system minimises the generation of wastewater. The operation at full
capacity is anticipated to generate approximately 7,000 L per day of wastewater from operation of
the bioreactors, processing of algal cell mass and cleaning activities. All water used in the
production system will undergo ultrafiltration and ultraviolet treatment; wastewater will be
transferred into a holding tank and undergo dose chlorination prior to discharge to the sewer to
ensure that no viable organisms are discharged to waste.
Airborne Emissions
The cultivation of algae in closed system bioreactors will not generate emissions of dusts, vapours,
gases or other airborne contaminants. Any airborne emissions within the production facility,
generated independently of the closed bioreactors, will be filtered through the HVAC system (hepa
filtered) to remove microbial and particulate matter.
Solid Waste Management
Minimal solid waste will be generated through the production process. Media packaging materials
will be appropriately recycled. In the event of unforeseen circumstances requiring the disposal of
algae, proper treatment will be conducted prior to discharge to ensure the absence of viable cells.
Noise Assessment
The planned procedures will utilise closed system bioreactors that operate exclusively within
enclosed workrooms located in a fully sealed building. It is expected that the noise levels originating
from the building will not surpass background noise level, making a Noise Management Plan
unnecessary at this point. If any alterations are made to the operations, noise levels will be
monitored accordingly.
The locality and proposal plan are included below.
Page 2 of 8
Document Set ID: 22408646
Version: 6, Version Date: 15/09/2023
Page 3
Figure 1 – Locality
Figure 2 – Site Plan
Page 3 of 8
Document Set ID: 22408646
Version: 6, Version Date: 15/09/2023
Page 4
2. SITE DETAILS
2.1. Background
A Development Permit for Material Change of Use for Industrial Business Type 2 (07/0340) &
Operational Works (07/0167) was issued In March 2007 subject to a number of conditions including
requirements for landscaping and car parking. It appears that some of the landscaping and line
marking of the car parking was not undertaken or has since been removed.
2.2. Site Description
The site is zoned Medium Impact Industry and has a total area of 6778m2 with a separate ingress
and egress provided from Action Street. A large industrial shed has been built on site with some
landscaping located to the site’s frontage and to the site’s western boundary. The site slopes up
from the roadway with a footpath constructed along the site’s frontage.
2.3. Surrounding Land Uses
The subject site is located within an industrial area and is surrounded by mixed industrial uses.
3. ASSESSMENT
3.1. Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following
statutory planning instruments to the extent they are relevant to the development:
• State Planning Policy;
• South East Queensland Regional Plan;
• Planning Regulation 2017; and
• Noosa Plan 2020.
3.2. Noosa Plan 2020
The site is located in the Noosaville Industrial estate and is zoned Medium Impact Industry. The
proposed use is defined as aquaculture and is identified as a consistent use for the site. The
application is required to follow a code assessment process, with the following codes applicable:
• Medium Impact Industry Zone Code;
• Noosaville Local Plan Code;
• Rural Activities Code;
• Works Codes;
The proposal is consistent with the applicable Codes and will contribute to the range of enterprises
and economic diversity in the Shire, expanding employment opportunities in the Shire.
The proposed operations have been designed to not harm the environment and avoid noise, odour
and other waste impacts on the surrounding area, with the use predominantly contained in an
enclosed environment within the existing building. The proposed use is of a type and scale that is
suitable for the industrial area and will not adversely impact on surrounding industrial operations,
where operated in accordance with its Environmental Management Plan. The proposed
aquaculture facility is associated with the existing research and technology industry operated on
site by Provectus Algae.
Inspection shows that existing landscaping to the site’s frontage to Action Street and to the rear
has been reasonably maintained but some has been removed or not installed pursuant to the
original approved plans. There is limited line marking of car parking on site, which would assist
operations and encourage on site car parking by staff and visitors to the site. A condition is
therefore recommended requiring a minimum of 15% of the site provided for landscaping and a
minimum of 17 car parking spaces line marked on site. This required landscape area and car
parking spaces is consistent with the acceptable outcomes of Noosa Plan 2020 codes.
Page 4 of 8
Document Set ID: 22408646
Version: 6, Version Date: 15/09/2023
Page 5
4. CONSULTATION
4.1. Referral Agencies
The applicant was referred to the Department of Infrastructure, Local Government and Planning
(SARA). The Department is a referral agency for Aquaculture (Schedule 10, Part 6, Division 1,
Table 1)
The Department has responded, approving the development subject to conditions, including
limiting the species types, requiring species to be sourced from the CSIRO National Algae
Collection and requiring the use to operate in accordance with the Environmental Management
Plan.
4.2. Internal Council Referrals
Not applicable
5. CONCLUSION & REASONS FOR DECISION
The proposed development generally complies with the requirements of the planning scheme and
does not raise any significant issues with the proposed operations and potential impacts to be
managed by the referral agency conditions. The application is therefore recommended for
approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No MCU23/0038 for a Material Change of Use - Aquaculture situated at
14-16 Action St, Noosaville and described as Lot 290 MCH 811938, it is recommended the
application be approved in accordance with the following details for the Decision Notice:
1. APPLICATION DETAILS
Application No: MCU23/0038
Street address: 14-16 Action St, Noosaville
Real property description: Lot 290 MCH 811938
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
Council decided to issue the following type of approval:
• Development Permit for a Material Change of Use - Aquaculture
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
Currency Period
2. This development approval lapses if the use has not happened by 11 September 2029,
unless an application to extend the currency period is approved by Council.
Page 5 of 8
Document Set ID: 22408646
Version: 6, Version Date: 15/09/2023
Page 6
Approved Plans
Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below.
Plan No. Rev. Plan/Document Name Date
PA-LAB-016 0.01 Site Layout3- 202220929 prepared by Provectus 14/02/2023
Algae
Nature and Extent of Approved Use
3. The Aquaculture facility must be limited to the culture of marine and freshwater microalgae
species in closed system bioreactors and operated in association with an on site research
and technology industry.
Building Appearance
4. Waste storage areas, external approved storage areas, and mechanical equipment are
screened from the street.
5. No part of the site may be used for outdoor storage of materials unless specified on the
Approved Plans or the conditions of this Decision Notice. Materials stored outside of the
building must not exceed 4 metres in height or half the height of the building, whichever is
the greater.
6. All mechanical equipment and other service infrastructure located on the site must be:
a. located not less than 2 metres from a property boundary
b. fully enclosed or screened such that they are not visible from the street frontages nor
adjoining properties. Where screened by landscaping, landscaping beds must be at
least 1.5 metres wide.
Staff Amenities
7. On site amenities, including seating, tables and rubbish bins, must be provided for staff
protected from weather and removed from any noisy or odorous activities.
Landscaping Works
8. A minimum of 15% of the development site must be landscaped. The works must be
undertaken in accordance with Noosa Plan 2020 for that specific area and must include in
particular:
a. provision of one (1) 45 litre feature tree (Cupaniopsis anarcardioides or Banksia
integrifolia or Xanthostemon chrysanthus) in the north eastern corner of the
development site (on the northern side of the driveway);
b. provision of a minimum of four (4) 25-45 litre street trees (Cupaniopsis anarcardioides
or Banksia integrifolia or Xanthostemon chrysanthus) along the Action Street frontage,
located between back of kerb and the footpath; and
c. retention of the existing landscaping onsite.
9. All landscape works must be established and maintained for the life of the development, and
in a manner that ensures healthy, sustained and vigorous plant growth. All plant material
must be allowed to grow to full form and be refurbished when its life expectancy is reached.
Car Parking
10. A minimum of 17 car parking spaces must be provided and marked on site and made
available and accessible at all times for staff and visitors to the site while the use is open for
business. Vehicle manoeuvring areas are provided on site in accordance with the Australian
Standards for Off-street car parking so vehicles enter and leave the site in a forward gear.
Page 6 of 8
Document Set ID: 22408646
Version: 6, Version Date: 15/09/2023
Page 7
5. REFERRAL AGENCIES
The referral agencies applicable to this application are:
Referral Status Referral Agency and Referral Trigger Response
Address
Concurrence SARA at DILGP SARA Schedule 10, Part 6, The agency provided its
at DILGP Via MyDAS2 Division 1, Table 1 - response on 14 August
at Aquaculture 2023 (Reference No.
https://prod2.devasses 2306-35006 SRA). A
s.qld.gov.au/suite/ (for copy of the response is
assistance, contact attached
DILGP at 5352 9701 or
email:
[email protected]
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Advertising Devices
1. All Advertising Devices must comply with Schedule 10 of Subordinate Local Law No.1
(Administration) 2015 including both temporary and permanent signage. All freestanding,
pylon or pole signs or signage that is illuminated requires approval from Council prior to being
installed. All signage identified in s6 of Schedule 10 of Subordinate Local Law No. 1 is
prohibited from being erected in the Shire.
Infrastructure Charges
2. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
7. PROPERTY NOTES
Not applicable.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Building Works All building work.
10. SUBMISSIONS
Not applicable.
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
Page 7 of 8
Document Set ID: 22408646
Version: 6, Version Date: 15/09/2023
Page 8
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.
Page 8 of 8
Document Set ID: 22408646
Version: 6, Version Date: 15/09/2023
Used in these records
Delegated Report - Code - Planning MCU23 0038 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.6 MB (small file)
- File type
No other editions are linked here.