240808 - Sprout As Consturcted 9 BARTLETT RD NOOSAVILLE INDUSTRIAL WAREHOUSES - REV D (002)

of 26

Page text shows just the words. Original shows the document exactly as it was published.

Original PDF page 5, section 1. The text section number identifies this passage in the reader.

CONSTRUCTION   These hazards include the demolition of existing structures.

                                          HAZARD CATAGORY DETAIL OF HAZARD                                                                   RAW RISK LEVEL                                RECOMMENDED AND EXISTING                                                              REVISED RISK LEVEL                                   ACTION
                                                                                                                                                                                           CONTROL MEASURES
C1                                        Adjoining Areas          The site backs onto other industrial areas, potential for persons using                                                 Recommend that works are controlled and maintained within the                                                                              Principal/Maintenance/Demolition Contractor
                                                                   these areas to be injured.                                                                 4                            site boundaries.                                                                                           3

C2                                        Hazardous                Cutting of masonry blocks, potential inhalation of silica.                                                              Recommend minimising dust exposure through recomendations                                                                                  Principal/Maintenance/Demolition Contractor
                                          Substances                                                                                                          4                            of the materials safety data sheet.                                                                        3

C3                                        Hazardous                Exposure to chemical termite treatment.                                                                                 Recommend use of physical or low toxicity termite barriers where                                                                           Principal/Maintenance/Demolition Contractor
                                          Substances                                                                                                          4                            appropriate.                                                                                               3

C4                                        Hazardous                Treated timber used in construction.                                                                                    Consider using less hazardous treated timbers. Follow material                                                                             Principal/Maintenance Contractor
                                          Substances                                                                                                          4                            safety data sheet where appropriate.                                                                       3

C5                                        Hazardous                VOC fumes from paints and other coatings.                                                                               Recommend specifying the use of low VOC adhesives and                                                                                      Designer
                                          Substances                                                                                                          3                            finishes where possible.                                                                                     1

C6                                        Structural Stability     Construction of new steel and masonry structures, risk of potential                                                     Recommend provision of propping and support, obtain advice                                                                                 Principal/Maintenance Contractor
                                                                   collapse.                                                                                  4                            from Structural Engineer as required.                                                                      3

                                                                                                                                                                                           Contractor to prepare a Safe Work Method Statement prior to commencing
C7                                        Work at Height           High risk of falling as falls from a height greater than 2m are                                                                                                                                                                                                    Principal/Maintenance Contractor
                                                                   possible.                                                                                  4                            work. Provide edge protection to all roof and canopy edges to AS4994.                                      3
                                                                                                                                                                                           Provide roof safety mesh to AS4389.
                                                                                                                                                                                           Contractor to prepare a Safe Work Method Statement prior to commencing
C8                                        Confined Spaces          Sewer and stormwater manholes, service pits; risk of entrapment and                                                                                                                                                                                                Principal/Maintenance Contractor
                                                                   suffocation.                                                                               4                            work. Only workers with confined spaces training are permitted to enter                                    3
                                                                                                                                                                                           confined spaces.

C9                                        Climatic Conditions      Displacement of soil during a flood event.                                                                              Ensure tanks are decomissioned and anchored down during potential flood                                                                    Principal Contractor
                                                                                                                                                              4                            events. Include in emergency plan.                                                                         3

C10                                       Earthworks               Excavations for underground tanks and trenches, potential for                                                           Contractor to prepare a Safe Work Method Statement prior to commencing                                                                     Principal Contractor
                                                                   instability and collapse where depth exceeds 1.5m.                                         4                            work.                                                                                                      3

C11                                       Manual Tasks             Manual tasks associated with handling of large or awkward                                                               Contractor to prepare a Safe Work Method Statement prior to commencing                                                                     Principal Contractor
                                                                   construction elements.                                                                     3                            work. Recommend mechanical assistance.                                                                     2

C12                                       Electrical               Works on or near energised electrical installations are defined as                                                      Contractor to put in place a Safe Work Method Statement prior to                                                                           Principal/Maintenance/Demolition Contractor
                                                                   high risk construction work.                                                               4                            commencing works.                                                                                          3

                                                                   Temporary Plant - Works on or near mobile energised electrical
C13                                       Electrical                                                                                                                                       Contractor to put in place a Safe Work Method Statement prior to                                                                           Principal/Maintenance/Demolition Contractor
                                                                   installations are defined as high risk construction work.                                  4                                                                                                                                       3
                                                                                                                                                                                           commencing works.

C14                                       Electrical               Electrical pits located near hazardous zones, potential ignition                                                        Contractor to put in place a Safe Work Method Statement prior to                                                                           Electrical Engineer
                                                                   source.                                                                                    4                            commencing works.                                                                                          3

C15                                       Fire and Emergency       Egress from partially constructed building in an emergency.                                                             Recommend evacuation procedures are communicated in an                                                                                     Principal Contractor
                                                                                                                                                              4                            emergency plan as per S43 WHS Regulation.                                                                  3

C16                                       Hazardous                Installation and commisioning of fuel tanks.                                                                            Refer detailed manufacturer instructions. Ensure works are compliant                                                                       Client, Principal Contractor
                                          Substances                                                                                                          4                            with Sections 363-364 of WHS Regulations 2011                                                              3

C17                                       Hazardous                Installation of gas and fuel lines.                                                                                     Refer detailed manufacturer instructions. Recommend emergency                                                                              Principal Contractor
                                          Substances                                                                                                          4                            response to gas is included in the emergency plan.                                                         3

C18                                       Hazardous                Fibre cement used in construction, potential risk of silica inhalation                                                  Follow the recommendations in the product safety data sheet including working in                                                           Principal Contractor
                                          Substances               (fibre cement selected for durability and maintenance).                                    4                            a well ventialted area and personal protective equipment                                                   3

C19                                       Hazardous                Glass fibres and volatile organic compounds (VOC's) fumes from                                                          Recommend installing foil, polyester, natural or fibre bio-soluble insulation where                                                        Principal Contractor
                                          Substances               insulation.                                                                                4                            possible.                                                                                                    1

C20                                       Mobile Plant             Operation on uncompacted fill, potential for tipping.                                                                   Geotechnical report available for reference.                                                                                               Principal Contractor
                                                                                                                                                              4                                                                                                                                       3

C21                                       Mobile Plant             Operation of mobile plant over under ground tanks during                                                                Maintain exclusion zone around tanks during construction.                                                                                  Principal Contractor
                                                                   construction, potential for collapse.                                                      4                                                                                                                                       3

C22                                       Slips, Trips and Falls   Tanks have the potential risk for falls where excavation exceeds 2m.                                                    Recommend the use of appropriate barriers. Manage risk of falls as per S.78 WHS                                                            Principal Contractor
                                                                                                                                                              4                            Regulation.                                                                                                3




                                                                      REV    DESCRIPTION                         DRAWN DATE
                                                                                                                                                                                                                             project                                                drawing
                                                                     A      BUILDING APPROVAL                   AC/NN   03/08/22
                                                                     B      BUILDING APPROVAL                   AC/NN   12/08/22                                  Suite 2, Suncoast Resort Business Centre                   PROPOSED NEW INDUSTRIAL                                SAFETY IN DESIGN REPORT 2
                                                                     C
                                                                     D
                                                                            BUILDING APPROVAL
                                                                            B.A - AS BUILTS FOR CERTIFICATION
                                                                                                                KT/AC
                                                                                                                NN
                                                                                                                        13/09/22
                                                                                                                        08/08/24
                                                                                                                                                                  Cnr Gardak Street
                                                                                                                                                                    SUNCOAST        & Surf Road
                                                                                                                                                                                  RESORT      BUSINESS    CENTRE             WAREHOUSES
                                                                                                                                                                  Alexandra
                                                                                                                                                                    SUITE 2  Headland  Q 4572
                                                                                                                                                                               CNR GARDAK        ST & SURF RD                                                                                                                                                Copyright of this document remains the exclusive
                                                                                                                                                                                                                             for                                                                                                                             property of SPROUT ARCHITECTS PTY LTD
                                                                                                                                                                  POALEXANDRA   HEADLAND
                                                                                                                                                                      Box 6232, Maroochydore   BC Q 4558 Qld 4572                                                                                                                                            ABN 23 123 917 724.
                                                                                                                                                                    PO BOX 6232 MAROOCHYDORE BC             Qld 4558         OLD SEA DOG 9 PTY LTD                                  date 8/08/2024          drawn KT/AC scale AS SHOWN                       Contractors are to verify all dimensions and levels on
                                                                                                                                                                  P PH
                                                                                                                                                                    07 :5443  5028
                                                                                                                                                                         07 5443   F 07 5479 2380 | ABN
                                                                                                                                                                                 5028               FAX:07235479
                                                                                                                                                                                                             123 917
                                                                                                                                                                                                                 2380724     at
                                                                                                                                                                                                                                                                                                                              @ A1
                                                                                                                                                                                                                                                                                                                                                             site prior to commencing. Report all discrepancies to
                                                                                                                                                                  [email protected]
                                                                                                                                                                    ABN                       | sproutarchitects.com.au
                                                                                                                                                                                                       23 123 917 724        9 BARTLETT ROAD NOOSAVILLE QLD
                                                                                                                                                                                                                                                                                                                                                             the Architect. Use figured dimensions in preference
                                                                                                                                                                                                                                                                                                                                                             to scaled.
                                                                                                                                                                    EMAIL:                [email protected]                                                                   drawing no. 21015       CD10.04      revision D
Log in to download the original file

240808 - Sprout As Consturcted 9 BARTLETT RD NOOSAVILLE INDUSTRIAL WAREHOUSES - REV D (002).pdf · 8.5 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.