SITE SPECIFIC CONDITIONS
Bonds
3. A site control and/or compliance bond of $25,000 is to be submitted to Council prior to the
pre-start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
4. Bonds must:
a. have approval of the bond calculations and amount from Council prior to lodgement
b. be lodged with Council and accompanied by the Bond Administration Fee/s.
c. be requested for release by writing to Council, when relevant approval requirements
have been met.
PRIOR TO COMMENCEMENT OF WORKS
Landscaping
5. Tree protection fencing must be installed under the supervision of the qualified person*.
*(Refer to Advisory Note)
6. At the prestart and prior to clearing works a review of all clearing associated with or adjacent
to the Allocasuarina littoralis must be undertaken with the site arborist.
Engineering
7. Deleted.
8. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
9. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
10. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
11. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. civil engineering works;
b. landscape works;
c. erosion and sediment control works;
d. arboreal works;
e. fauna management works; and
f. other relevant parties
Page 4 of 16
Document Set ID: 23995807
Version: 4, Version Date: 05/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - OPW24 0125 01 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 195 KB (small file)
- File type
No other editions are linked here.