b. Fauna management works
c. Erosion and sediment control works
d. Other relevant parties
DURING WORKS
General
5. Where damage occurs to any Council asset as a result of the development works, it must be
repaired immediately where it creates a hazard that presents risk to person or property. Other
damage must be repaired prior to completion of works.
6. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice.
b. The relevant conditions of the higher order Material Change of Use approval viz.
Planning and Environment Court Judgment No. 3746 of 2023, to which this approval
relates.
c. All relevant Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines.
VEGETATION PROTECTION
Retention of Existing Trees and Vegetation
7. All trees and vegetation identified for retention must be protected in accordance with
AS 4970, Protection of trees on development sites and the relevant approved documents
and plans of this decision notice.
8. A qualified person* must be engaged for the duration of the works to:
a. Ensure works are carried out in accordance with the approved Arborist Report and
approved Concept – Construction and Tree Management Plan.
b. Oversee installation of all tree protection fencing prior to commencement of any
clearing works onsite.
c. Supervise tree protection within the development site and frontages, prior to, during
and following construction in accordance with AS 4970, Protection of trees on
development sites.
d. Oversee approved tree removal in proximity to retained trees.
*(Refer to Advisory Note)
9. Vegetation areas for protection must:
a. Be protected in accordance with the approved Arborist Report and approved Concept
– Construction and Tree Management Plan.
b. Be protected with a 1.8m high temporary safety fence (or temporary barrier mesh).
c. Have the fence installed prior to the prestart meeting and maintained for the entire
period of construction.
d. Have ‘Exclusion Zone’ (‘No Go’) signage fixed to the fence at 10m centres.
e. Have no construction material, equipment or personnel entering the ‘Exclusion zone’
(‘No Go’) except to undertake approved rehabilitation activities.
*(Refer to Advisory Note)
Fauna Management
10. A qualified person* must be engaged to manage fauna prior and during clearing to:
Page 3 of 38
Document Set ID: 24866398
Version: 5, Version Date: 16/06/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice OPW25 0206 (AS Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.0 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.