8. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
9. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
10. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
11. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the final inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as in
the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
Retention of Existing Trees
12. The existing trees on adjoining properties must be retained and protected during construction
wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
construction of the development which is the subject of this development approval.
Removal of Existing Trees and Vegetation
13. Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
well as optimum weed seed sterilisation.
Qualified Person
14. Qualified Person, for the purpose of:
a. Supervising landscape works and preparing a landscape certification, is considered to
be a landscape architect, landscape designer or horticulturist with a minimum of three
years current experience in the field of landscape design.
b. Undertaking landscape construction and establishment works is considered to be a
person with five years current experience in commercial landscape construction
projects.
c. Undertaking, supervising tree works and preparing arboriculture certification, is
considered to be a person with a minimum three years current experience in tree
protection, hazard identification/mitigation and assessment and either:
iii. International Society of Arboriculture (ISA) certification; or
iv. A Diploma of Arboriculture.
d. Undertaking Fauna site works and calculating compensatory habitat is considered to
be a Fauna Spotter Catcher with current certification under the Queensland Parks and
Wildlife Service.
e. Preparing certification and managing declared plant pests, is considered to be:
Page 13 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Negotiated - OPW22 0299 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 168 KB (small file)
- File type
No other editions are linked here.