ORDINARY MEETING MINUTES 25 SEPTEMBER 2014
Fencing and Walls
12. Any street fencing must be set back an average of 1 metre from the front
property boundary. Any fencing on the front boundary must either:
a. not exceed a maximum height of 1.2m; or
b. be of open construction.
13. The area of land between the fence and the front property boundary must be
densely landscaped to screen any fencing from the street.
Community Management Statement
14. Any proposed Community Management Statement required for the
development pursuant to the Body Corporate and Community Management Act
1997 must be submitted to Council for endorsement at the same time as
submission of the Building Format Plan (or similar) to Council for compliance
assessment.
15. All clauses and by-laws of the proposed Community Management Statement
must accord with the requirements of this Decision Notice
Waste Management
16. Refuse storage, removal and collection facilities must be provided in
accordance with the following:
a. provision of a minimum of two 240L wheelie bins for each dwelling unit;
b. provision of separate bins for general and recyclable waste for each
tenancy, with an equal number of each being provided; and
c. provision of a hardstand impervious area in accordance with the
approved plan.
Unitywater
17. Reticulated water supply and sewerage must be provided to the development.
18. Construction activities must not impede the access of Unitywater or Fire
Brigade personnel to vital infrastructure (eg. valves, fire hydrants and sewer
access chambers).
19. The fire-fighting demand on Unitywater’s water supply system from the
development must not exceed 15 litres per second.
20. A single Unitywater installed primary water meter must be provided immediately
inside the property boundary. Meters must be Unitywater approved, installed in
accordance with Unitywater requirements and remain accessible at all times for
reading and maintenance purposes.
21. Sub meters must be provided at the boundary of each title to be administered
by a body corporate.
22. The existing 100mm diameter AC watermain within Nannygai Street must be
replaced for the full frontage of the development site with DICL pipes. The
replacement works must be completed prior to placing construction
materials/site offices over or adjacent to the water main alignment.
23. Easements of between 3 and 10 metres must be provided over all Unitywater
sewers located within property boundaries in accordance with the SEQ
standards. Easements shall be centred over the pipe. Easement terms shall be
the most current registered dealing held by the Department of Natural
Resources & Mines and shall not be altered or amended.
24. Water meters must be located on alternative boundaries to electrical pillars.
Page 9 of 27
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.