ORDINARY MEETING MINUTES 25 SEPTEMBER 2014
25. Buildings and other structures must maintain a minimum clearance of 1.5
meters from Unitywater sewer mains, and 1.0 meter from a sewer manhole
chamber or sewer inspection opening.
26. Storm water retention systems and gross pollutant traps must maintain a
minimum clearance of 1.5 meters from Unitywater water supply and sewerage
infrastructure.
27. The applicant must adjust the level of the existing sewerage inspection opening
as necessary to suit the proposed finished levels. Work must be undertaken by
Unitywater at the owner’s cost. Where the existing sewerage inspection
opening point is located within a sealed or concreted parking area, a brass cap
is required to be fitted.
28. Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from
Unitywater water mains and 1.5 metres from Unitywater sewerage mains.
Landscaping plants within these clearances must be low growing when mature,
and suitable approved varieties.
29. Construction works undertaken in the vicinity of Unitywater water supply or
sewerage infrastructure must not adversely affect the integrity of the
infrastructure. All costs associated with repair, replacement or alteration of
infrastructure must be met by the applicant.
ENGINEERING
External Works
30. Nannygai Street must be upgraded for the length of its frontage to the subject
site. The works must include in particular:
a. Construction of a pedestrian footpath in accordance with the conditions of
this Decision Notice; and
b. Removal of the existing property accesses, stormwater outlet points and
reinstatement of the kerb, footpath and verge area to match the balance
of the site frontage, including the provision of topsoil and turf where the
existing verge is grassed.
This condition is imposed pursuant to s665 of the Sustainable Planning Act
2009 being non-trunk infrastructure.
Site Access and Driveways
31. A sealed access driveway must be provided from Nannygai Street to all parking
and manoeuvring areas of the development. The works must include in
particular a driveway crossover in accordance with IPWEAQ standard drawing
SEQ R-051with a maximum width of 6 metres at the property boundary.
Car Parking
32. A minimum of 9 car parking spaces must be provided and marked on the site.
The works must include crossfalls, gradients and dimensions in accordance
with Australian Standard AS2890: Parking Facilities
33. All vehicles must enter and exit the site in a forward gear.
Footpath
34. A pedestrian and bicycle footpath must be provided for the development. The
works must include in particular a 2.0 metre wide footpath within the road verge
for the entire length of the site’s frontage to Nannygai Street. This condition is
imposed pursuant to s665 of the Sustainable Planning Act 2009 being non-
trunk infrastructure.
Page 10 of 27
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.