Landscape Technical Specification - OPW14/0197
Attached to the e-mail Doonella Stage C (Email 7 of 7) Landscape Technical Specification & Transmittal - OPW14/0197.
Doonella – Stage C
1. PRELIMINARIES
1.1 SCOPE OF WORK
The scope of the works to be undertaken under this contract are depicted on the drawings included in the
Tender documents, as described in the Specification and qualified in these Preliminaries.
The works to be performed are set out in the following drawings and comprise of the following:
AS 2124 General Conditions of Contract (available on request)
Landscape Management Plan (available on request)
Tender Schedule
Technical Specification
The following drawings:
Sheet No. Issue Dwg Title Scale
L-001 OP2 Cover Sheet NTS
L-002 OP2 Legend & Schedule NTS
L-201 OP2 Surface Finishes Plan 1:200
L-202 OP2 Surface Finishes Plan 1:200
L-203 OP2 Surface Finishes Plan 1:200
L-204 OP2 Surface Finishes Plan 1:200
L-205 OP2 Surface Finishes Plan 1:200
L-206 OP2 Surface Finishes Plan 1:200
L-207 OP2 Surface Finishes Plan 1:200
L-208 OP2 Surface Finishes Plan 1:200
L-401 OP2 Planting Plan 1:200
L-402 OP2 Planting Plan 1:200
L-403 OP2 Planting Plan 1:200
L-404 OP2 Planting Plan 1:200
L-405 OP2 Planting Plan 1:200
L-406 OP2 Planting Plan 1:200
L-407 OP2 Planting Plan 1:200
L-408 OP2 Planting Plan 1:200
L-901 OP2 Landscape Details As Indicated
L-902 OP2 Landscape Details As Indicated
L-903 OP2 Landscape Details As Indicated
L-904 OP2 Landscape Details As Indicated
One copy of the Contract Documents shall be issued to the Contractor. The Contractor shall be deemed to
have examined the documents and to have allowed for all costs in the tender in relation to the provisions of
these documents affecting the work.
The Schedule of Items does not quantify the works or the full list of items required to be undertaken. This
Schedule is to be used for tender evaluation and as an indication of the value of work completed for
Progress Payment Purposes only.
Requirements of individual technical sections of the specification take precedence over any conflicting
requirements in the preliminaries.
Check all relevant dimensions on site before proceeding with work. Under no circumstances shall
dimensions be scaled from drawings. No claim for extras arising from failure to obtain measurements and
other information on site will be allowed.
AECOM 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.