                 60.    A detailed assessment of all existing and proposed mechanical plant, equipment and
                        other service infrastructure located on the site must be carried out in accordance with
                        the criteria detailed in condition 45.
                         Evidence of compliance with this condition must be provided to Council prior to the
                         commencement of use, and the mechanical plant must be maintained in accordance
                         with the approved acoustic treatment for the life of the development.
                 61.    When requested by Noosa Council, a Noise Impact Assessment Report (NIAR) showing
                        monitoring and recording of noise levels must be undertaken to investigate any non-
                        vexatious complaint caused by noise emissions from operations at the premises. Such
                        monitoring must be undertaken and completed within a reasonable and practicable
                        timeframe as nominated by council and be performed by a suitably qualified and
                        experienced person.
                         The NIAR must be submitted to Council detailing the results of such monitoring and
                         recommendations for any measures to achieve compliance with limits outlined in Table
                         1 of this Decision Notice.
                 62.    Measurement of sound pressure levels (adjusted for tonality and impulse) must be in
                        accordance with Australian Standard AS1055.1 “Acoustics – Description and
                        measurement of environmental noise – General procedures”.
                         For the purpose of measuring and certifying relevant noise conditions and reporting (e.g.
                         mechanical plant and equipment, a/c units, motors, refrigeration equipment,
                         compressors, pumps etc), a suitably qualified person is either:

                        a.      Registered Professional Engineer of Queensland, or
                        b.      an environmental consultant with a minimum of 3 years current experience in the
                                field of acoustics.
                 63.    Any future mechanical plant should be selected to ensure compliance with the
                        established noise criteria in Section 3 of the approved Noise Impact Assessment Your
                        Mates Bowls Pub, referenced #1859d1-B prepared by Live It Acoustics and dated 6
                        March 2025.
                EASEMENTS
                 64.    Where the development site has frontage to Diamond Lane, the applicant must dedicate
                        a 2 metre wide easement along the full length of this laneway frontage for the purpose
                        of future laneway widening and upgrading. The easement must be provided prior to the
                        issue of the building approval and be registered in favour of the relevant local
                        government authority.
                 65.    The terms of the easement must allow for the use of the easement by the public whether
                        in vehicles, cycles or on foot.
                 66.    All easements must be designed in accordance with the planning scheme and granted
                        at no cost to the Grantee. Where the Grantee is Council or a service authority, the
                        easement documentation must be in accordance with the Grantee’s standard easement
                        terms. Draft easement documentation must be submitted to Council for endorsement.
                 67.    All works must be kept clear of any existing or proposed easements on the subject land,
                        unless agreed otherwise in writing by the Grantee.
                 68.    Unless otherwise agreed in writing by the relevant service provider, any public or third
                        party infrastructure located on the subject site must be placed within an easement
                        registered against the title of the property.




                                                                                                        Page 9 of 14
Document Set ID: 24239488
Version: 7, Version Date: 23/10/2025
Log in to download the original file

Other Change Decision Notice - Council Meeting Decision 51995 1611 04 (As Published).pdf · 218 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.