SERVICES & ORGANISATION COMMITTEE MEETING 8 AUGUST 2023
Projects with Grant Funding 66% Refer figure 2 for more
detail
Figure 1
Figure 2 detail Percentage Value
of CWP of CWP
Non grant projects 34% $21.1m
Grant funding revenue 36% $20.2m
Council's contribution to 31% $17.3m
projects with grant funding
Figure 2
4. Completed Projects
While the 4th quarter continues to experience a heated construction market with ongoing material
shortages, lengthy lead times, pricing increases and contractor availability issues; 79% of capital
expenditure has been completed to date this quarter. The Project Control Group and Capital
Works Executive have continued to enable staff and Council to make informed decisions that
relate to projects being delivered throughout the year.
This quarter has seen the successful completion of the following key projects:
Page 12 of 23
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.