Information Request OPW23 0179 · OPW23/0179
Officer: Mark Lewis
Direct Telephone: 07 53296290
Our Reference: OPW23/0179
Your Reference: 220508
13 December 2023
CE Cullen & M Cullen
C/- DME Projects
POBox 7481
SIPPY DOWNS QLD 4556
[email protected]
Dear Sir
Information Request
Planning Act 2016
I refer to your application and advise that Council requires further information to satisfactorily
assess the proposal.
1. APPLICATION DETAILS
Application No. OPW23/0179
Street Address: 128 Gympie Tce Noosaville Qld 4566
Real Property Description: Lot 1 MCH 3881
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. INFORMATION REQUIRED
The information requested is set out below:
Issue
The applicant has not fully demonstrated compliance with conditions of the higher order
approval MCU22/0171.
Information Required
i. Provide the amended plans as described in Condition 2
ii. Provide the bond as described in Condition 6. It is noted that the bond must be received
prior to the issue of the subject operational works approval.
iii. Demonstrate compliance with Condition 24 – Waste Management
Issue
Council has concerns that the proposed contiguous pile wall will impact on the ability to provide
dense deep landscaping around the building. It is noted that the development of the adjoining
site has recently installed drilled/driven sheet piling.
Information Required
2. Provide further advice on the proposed retaining wall methods to be employed on site.
If an alternate method to contiguous piles is proposed, provide amended plans.
PO Box 141 P. (07) 5329 6500 [email protected]
TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au
Page 1 of 3
Document Set ID: 22730091
Version: 2, Version Date: 15/12/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
Issue
Flooding and access to the basement. The driveway ramp to the basement does not
incorporate the required 300mm freeboard above the defined flood level (DFE).
Information Required
3. Amend the driveway and access design to ensure that 300mm freeboard above the DFE
is achieved for all openings to the basement or provide a passive flood barrier system
which will achieve the equivalent level of protect and flood immunity for the basement.
Issue
The submitted dewatering management plan requires amendment.
Information Required
4. Provide an updated dewatering management plan that includes the following:
i. The DMP states that the shoring design is provided in Appendix C – however only
the civil engineering plans are provided. Include plans which show the location and
type of temporary shoring, groundwater spears, treatment and monitoring equipment
location and space requirements. Why do the structural engineering plans (provided
separately) only show shoring on 3 sides of the excavation? The type of CFA piling
(contiguous or secant) should also be stated on plan
ii. Remove references to ‘steel sheet piling’ on page 10 and refer to CFA secant piling.
Please note that the references should reflect the proposed method or the alternate
method chosen by the civil engineer.
iii. Update section 6.5.2 and 6.5.3 (Water Quality Monitoring) to include continuous
monitoring of pH and dissolved oxygen at the release point from the treatment
system. Total iron and aluminum are to be sampled where identified in the document
as ‘if required’.
iv. Update the figure in Appendix A to also show the stormwater network and specifically
the stormwater pit which the dewatering system will discharge into and the outlet
headwall.
v. Update section 6.4.3 to identify that discharge is to the stormwater network prior to
entering the canal system.
vi. There seems to be plenty of room in the frontage of the site for establishing a
groundwater monitoring bore outside of the excavation and shoring system in which
to monitoring groundwater drawdown and quality. Update the monitoring section of
the DMP to incorporate such a monitoring location.
vii. Section 7 (Noise) is to be updated to refer to the default noise standard for pumps
in Section 440T of the EPAct. The EEP (Noise) objectives currently referenced are
long-term objectives rather than a specific enforceable standard.
viii. Provide dilapidation reports for neighbouring properties and any other structures or
infrastructure identified as being within the estimated cone of depression associated
with the groundwater drawdown.
Issue
A number of the submitted engineering plans are stamped “not for construction” and have not
been signed by the RPEQ.
Page 2 of 3
Document Set ID: 22730091
Version: 2, Version Date: 15/12/2023
Page 3
Information Required
5. Provide amended plans that are for approval and construction and are signed by the
RPEQ.
3. DUE DATE FOR RESPONSE TO INFORMATION REQUEST
The due date for providing the requested information is 13 March 2024. Email your response
to [email protected]. Please advise Council of your response to this information request
in accordance with section 13 of the Development Assessment Rules.
If you do not provide a response before the due date, it will be taken as if you have decided
not to respond to the information request and Council will continue with the assessment of
your application.
4. OTHER DETAILS
You can follow the progress of this application online at www.noosa.qld.gov.au. The “Online
Services” page can be accessed via "Quick Links" on the left hand side of the screen.
Should you have any further queries in relation to the above, please do not hesitate to contact
me on the number above.
Yours faithfully,
Mark Lewis
Coordinator Engineering
Page 3 of 3
Document Set ID: 22730091
Version: 2, Version Date: 15/12/2023
Used in these records
Information Request OPW23 0179.pdfRelated documentApplication case desk ↗
About this file
- File size
- 113 KB (small file)
- File type
No other editions are linked here.