Appendix J - Civil Engineering Report and SBSMP
Noosa Residential Development
Ref: 24553 C R002 REV03 10.08.21.docx
August 2021
7 STORMWATER QUALITY ASSESSMENT
7.1 Treatment Objectives
This assessment identifies issues relating to stormwater quality runoff and assesses possible
methods of treatment if required. The aim of this section of the report is to determine practical
approaches to achieving improvements in the quality of the stormwater run-off from the site that can
be readily implemented.
The SPP 2017 proposes assessment benchmarks criteria which apply to ‘high-risk’ development for
stormwater. The criteria include one or more of the following:
A Material Change of Use (MCU) for an urban purpose which involves a premises greater than
2,500m2 of land and;
will result in an impervious area greater than 25% of the net developable area; or
will result in six (6) or more dwellings;
A Reconfiguration of a Lot (ROL) for urban purposes that involves a land area greater than
2,500m2 and will result in six (6) or more lots; or
Operational works for urban purposes that involve disturbing more than 2,500m2 of land.
The proposal includes an MCU for a land area of 10,113 m2 that will result in impervious area equal
to 56% of the developable area. Hence, the development is classed as ‘high risk’ for water quality
and the SPP 2017 assessment benchmarks requirements will apply for the development.
The SPP 2017 suggests the development aims to:
Avoid or otherwise minimises adverse impacts on the environmental values of receiving waters,
arising from:
Altered stormwater quality and hydrology;
Wastewater (other than contaminated stormwater and sewage);
The creation or expansion of non-tidal artificial waterways;
The release and mobilisation of nutrients and sediments;
Development achieves the applicable stormwater management design objectives outlined in
Tables A and B (SPP Appendix 2); and
Development in a water supply buffer area avoids adverse impacts on drinking water supply
environmental values.
Appendix 2 (Table B) of SPP 2017 and Noosa Shire Council water quality and drainage code
suggests ‘Post Construction Phase – Stormwater Management Design Objectives’ as:
Table 6 - South East Queensland (SEQ) Targets
Total Suspended Solids Total Phosphorus Total Nitrogen Gross Pollutants
(TSS) (TP) (TN) >5mm
80% Removal 60% Removal 45% Removal 90% Removal
The objective is to provide the following:
Nitrogen and Phosphorous removal;
Gross Pollutant and Suspended Solids removal;
BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH Page 15
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix J - Civil Engineering Report and SBSMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.