Original source · versioned page text
Appendix J - Civil Engineering Report and SBSMP
Noosa Residential Development
Ref: 24553 C R002 REV03 10.08.21.docx
August 2021
EXECUTIVE SUMMARY
ADG Engineers (Aust.) Pty Ltd has been engaged by Stockwell Development Group, to prepare a
Site Based Stormwater Management Plan suitable for submission to Noosa Shire Council as
additional information in support of a Development Application for a Material Change of Use at Lot 3
on SP246584, 17-19 Hofmann Drive, Noosaville QLD 4566.
The proposed development as shown in Mode Design architectural plans is for three (3) multi-storey
residential buildings over a shared basement. The building work for the proposed development is to
form part of separate application submitted to Council for building approval.
This report is comprised of stormwater quantity and quality assessments. The quantity assessment
is undertaken to confirm a ‘non-worsening’ of peak flow discharges from the site and the quality
assessment is undertaken to determine the required stormwater treatment measures to be
implemented on site.
The stormwater quantity objective was to demonstrate that there are no impacts from storm events
up to and including the 1% AEP storm event, which will ensure that the existing infrastructure and/or
downstream properties are not adversely affected. It has been determined through the use of
hydraulic modelling that 14.0m3 of On-Site Detention that occurs over the proposed bioretention
basins is adequate to mitigate the impact of the proposed development and ensure post-
development peak flows do not exceed pre-development peak flows.
Currently no quality stormwater management measures are in place for the proposed Noosa
Residential Development. Stormwater treatment measures are to be implemented on site in
accordance with Industry Best Practice, WSUD Engineering Guidelines and the Noosa Plan 2020 to
provide stormwater treatment for this site. The table below provides a summary of the stormwater
management measures required for the proposed development
Catchment Quantity Mitigation Requirement Quality Mitigation Requirement
B1 9.7m3 of storage over bioretention 80m2 Bioretention
B2 4.3m3 of storage over bioretention 45m2 of Bioretention
Grass-lined swales that promote settlement
B3 Nil
of particulates.
All relevant standards and guidelines are addressed in this Stormwater Management Plan including
criteria from the Noosa Shire Council Planning Scheme Policies, Queensland Urban Drainage
Manual 2016, State Planning Policy 2017 Plumbing and Drainage Code AS3500.3 and Australian
Rainfall and Runoff Guideline.
BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH Page 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Appendix J - Civil Engineering Report and SBSMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.