Construction Environmental 06683025-3000{AA)
Management Plan October 2006
Commercial Development

Rev: 000 Page 8
Eenie Creek Road, Noosaville

 

 

 

 

 

11.4 Concerns Register

Complaints will be directed to the Project Manager who will issue the concern to the
appropriate personnel for action.

A hard copy record of all concerns will be kept at the Site office and filed for future
reference, if required. (Form 1).

The concerns register will record the following information:

1. Details: Name, address and phone number.

2. Nature of concern: Detail of issue, date of incident, people involved, and location.

3. Action taken or required: Any action proposed or undertaken to address the concern,
including time and date.

4. Response to Action: Was the complainant satisfied with the outcome of the actions
taken, if not, what else needs to be done, or is it outside the scope of the development
works.

5. Prevention or re-occurrence: What action has been taken by the nominated responsible
person to ensure the problem will not re-occur.

11.5 Rectification Requests and Instructions

Non-conformances will be documented on the Inspection and Monitoring Form. The form
states the nature of the non-conformance and the mechanisms implemented to rectify the
problem.

A copy of this form shall be undertaken by the Project Manager on a monthly basis,
immediately in the case of emergencies, or significant non-conformance.

12.0 TRAINING

All site staff of the Project Manager and contractors, will be required to undergo a site
induction covering all the elements of the EMP. The induction will aim to instil
environmental awareness in personnel and:

e Introduce and explain the duty of care required under the Environmental Protection Act
1994.

¢ Introduce the Environmental Management Plan (EMP) and responsibilities it places on
all contractors and consultants.

e Explain the various subordinate components of the EMP and the reporting and
monitoring procedures of the EMP and how they work.

Golder Associates

Used in these records

About this file

File size
10.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Application part 3 [As Published].pdf · 10.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.