Appendix F —- Waste Management Revision No: 000
Construction Stage October 2006 -
Environmental Procedures
Commercial Development
Eenie Creek Road.

2of 3

 

 

 

 

 

5. Provide dedicated bins for disposal of the following waste | Project Manager
streams: Concrete, timber, plasterboard, steel, plastics, general
waste, and Regulated Waste”, and dealt with according to the
waste disposal table outlined below.

 

6. Waste disposal is to be undertaken according to the Identify | Project Manager
recycling options for waste streams collected and implement
procedures to ensure these waste disposal options are
followed.

 

7. Educate staff and contractors as to the correct disposal of | Project Manager
waste materials.

 

8. Follow the Waste Management hierarchy: waste avoidance, | Project Manager
waste re-use, waste recycling, energy recovery from waste,
waste disposal for all materials used on site.

 

9. Fence the site to prevent wind blown waste from leaving the | Project Manager
site.

 

 

 

 

F4. INSPECTION AND MONITORING

The following inspection and monitoring program will be conducted at the site.
The results of these activities will be recorded on the inspection/monitoring
data sheets provided.

Activity Frequency Responsibility

 

 

1. Monitor areas, such as wire fences, | Weekly Project Manager
where litter may accumulate from
sources external to the site. Remove
any such litter and dispose of into bins.

 

 

 

 

 

2. Inspect designated concrete mixing and | * Weekly Project Manager
wash up areas. e After each
major rainfall
event*
3. Inspect designated paint wash up areas.__| Weekly _ Project Manager
4. Inspect waste disposal bins for correct | Weekly Project Manager
placement of waste materials
5. Sediment traps free of waste. Weekly Project Manager
6. Inspect fences for wind blown waste. Weekly Project Manager

Remove Waste.

 

 

 

 

 

*> 25mm within a 24 hour period.

 

2 Regulated Waste — as defined by the Environmental Protection Policy 2000.
Golder Associates 06683025-3000(AA)

Used in these records

About this file

File size
10.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Application part 3 [As Published].pdf · 10.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.