G Engineering Report And Plans · 132007.2398
Attached to the e-mail 132007.2398.02 Request to change existing approval (2 of 3) Engineering report & plans, Stormwater Plan.
Plans and drawings: the text below has words only, no drawings.
Very large file (10.6 MB): may take a few minutes to open.
CALIBRE CONSULTING
Specific Outcomes Probable Solutions Proposed Measures
(if code assessable)
(b) Is designed to be compatible with existing
infrastructure; and
(c) Is deigned using materials that are suitable for the
use, durable, easy to maintain and cost effective,
taking into account the whole of life cycle cost and
Council’s maintenance inventory.
O2 Water supply infrastructure is constructed: S2.1 Water supply infrastructure is constructed in All water supply infrastructure will be constructed and tested
accordance with Section 6 of PSP 6 – Engineering Design in accordance with Unity Water requirements.
(a) in accordance with appropriate engineering
Standards – Water and Sewerage;
standards; and
AND
(b) to minimise adverse environmental impacts.
S2.2 Erosion and Sediment control measures are designed Erosion and sediment control measures will be prepared as
and implemented in accordance with the Institution of part of the operational works (civil) design drawings.
Engineers Australia (Qld Division) Soil Erosion and
Sediment Control – Guidelines for Queensland Construction
Sites.
O3 Water supply infrastructure is proven to be suitable No solution provided. Water supply infrastructure will be constructed and tested to
for its use prior to Council accepting the dedicated Unity Water’s satisfaction prior to hand over.
asset.
O4 Water supply infrastructure is provided with all No solution provided. Water supply infrastructure will be supported by all required
supporting technical documentation. technical documentation.
O5 Where buildings or other structures are in proximity S5.1 The footing of any building or structure is located clear All existing infrastructure will be protected from the proposed
to Council’s water supply infrastructure, provision is of the zone of influence but no closer than 1.5m (measured works.
made to protect the infrastructure from physical horizontally) from infrastructure including sewers, water
damage and to allow ongoing maintenance by Council. mains and stormwater structures.
AND
B14158.W | COOROY RETIREMENT COMMUNITY | PALM LAKE RESORTS CIVIL ENGINEERING REPORT | 35
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
G ENGINEERING REPORT AND PLANS.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.