86.   The excavation of the site and the construction of the proposed works must not have any
      adverse affects on the stability of adjoining buildings and/or structures and/or services and/or
      lands. In this regard a Registered Professional Engineer Queensland must supervise the
      excavation of the site and the construction of the new works to determine whether any
      additional measures are required to protect the stability of adjoining buildings and/or structures
      and/or services and/or lands.
Acid Sulphate Soils
87.   A report on the Identification and Mitigation of Acid Sulphate Soils, prepared in accordance
      with Part 6 of SPP2/02 Guideline: Planning and Managing Development Involving Acid
      Sulphate Soils is to be submitted for approval by the Chief Executive Officer 5 working days
      prior to the commencement of any new building works.
Construction & Demolition Issues
88.   A Condition Survey must be carried out on adjoining buildings, structures and services prior to
      any demolition, excavation or construction works taking place on site. If distress already
      exists, a photographic survey should be undertaken, the distress measured and a plan to
      monitor changes to distress shall be implemented.
89.   A Demolition & Construction Management Plan for the development shall be submitted to and
      approved by Council at least 5 working days prior to the commencement of any Demolition or
      Building works or at least 5 working days prior to the pre-start meeting for Operational Works.
      The Demolition & Construction Management Plan shall include but not be limited to:
      89.1    Site working hours;
      89.2    Communication and consultation processes with surrounding premises and Hastings
              Street stakeholders;
      89.3    Control and suppression of:
              89.3.1 Noise
              89.3.2 Vibration
              89.3.3 Dust
              89.3.4 Odours and exhausts control; &
      89.4    Employee and contractor induction and education processes.
90.   A Traffic Management Plan for the each separate demolition and construction phase of the
      development shall be submitted to and approved by Council at least 5 working days prior to
      the commencement of any Demolition or Building works or at least 5 working days prior to the
      pre-start meeting for Operational Works. The Traffic Management Plan shall include but not
      be limited to:
      90.1    Limiting the routes for the heavy vehicles to the major road network and prohibit the
              use of the local roads as access to the site;
      90.2    Maintaining pedestrian access and safety along the site’s Hastings Street frontage;
      90.3    Indicate provision for on-site and off-site parking and shuttle buses for the required
              workforce;
      90.4    Indicate the location of loading and unloading areas,
      90.5    Indicate the location of any “holding” areas for heavy vehicles and
      90.6    Operating hours.
91.   Demolition of the existing development(s) on the site shall not be undertaken during the peak
      Christmas School Holiday period.

                                                                                     Page 11 of 25

Used in these records

About this file

File size
399 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Recommendation - Noosa Iconic Panel - 010.2008.00001787.001 [As Published].pdf · 399 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.