92. Construction and Demolition staff shall not park within the Hastings Street area, including the
surrounding streets, Lions Park or Noosa Parade. Parking shall either be on site or at a
suitable off-site location serviced via a shuttle bus. Details shall be included in the Traffic
Management Plans for the site.
Erosion and Sediment Control
93. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General (Engineering)
94. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which shall be
submitted in conjunction with an application for a Development Permit for Operational Works.
In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
submitted in conjunction with any application for Operational Works.
95. Digital detailed designs including drawings, calculations, specifications and a schedule of
works, shall be submitted with any application for a Development Permit for Operational
Works in respect of stormwater drainage works. The design shall be in accordance with
Council’s Planning Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage
and Earthworks. To avoid conflict with underground pipes or services, all existing and
proposed services required by the development shall be shown on the plans.
96. To facilitate production of As Constructed drawings it is suggested that all design drawings are
submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
use of ADAC are available at www.adac.com.au).
97. A construction management plan/strategy to ensure no damage occurs to Council services
shall be prepared by a suitably qualified Registered Professional Engineer and submitted to
Council in conjunction with any application for Operational Works.
98. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
99. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
100. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
101. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
type of all services and structures. All of which shall be submitted to Council for checking and
for Council’s records.
The data must fully detail levels for all engineering works including but not limited to drainage
structures, finished ground levels and pavement surface levels. The data shall be submitted in
the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
are available at www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
Page 12 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Recommendation - Noosa Iconic Panel - 010.2008.00001787.001 [As Published]Related documentApplication case desk ↗
001A9300.001.pdfRelated documentPublic source context ↗
About this file
- File size
- 399 KB (small file)
- File type
No other editions are linked here.