TIA - Application decision - s62A (PA) - Approval_1
Attached to the e-mail RAL26/0011 - SARA response with conditions.
before an appeal about the decision can be lodged in the Planning and Environment Court. A
copy of the Appeal Provisions under TIA and TPCA is attached in Attachment C for information.
Further approvals
The Department of Transport and Main Roads also provides the following information in relation to
this approval:
1. Road Access Works Approval Required – Written approval is required from the department to
carry out road works that are road access works (including driveways) on a state-controlled road
in accordance with section 33 of the TIA. This approval must be obtained prior to commencing
any works on the state-controlled road. The approval process may require the approval of
engineering designs of the proposed works, certified by a Registered Professional Engineer of
Queensland (RPEQ). Please contact the department to make an application.
General advice
The Department of Transport and Main Roads advises that Road Access Works are not required to
establish the existing access to McKinnon Drive. Road access works may be required in the future
in order to maintain the approved access at no cost to the Department of Transport and Main
Roads.
If further information about this approval or any other related query is required, the North Coast
Region Corridor Management Team of the Department of Transport and Main Roads should be
contacted by email at [email protected] or on (07) 5451 7055.
Yours sincerely
Helena Xu
Senior Town Planner
Attachments: Attachment A – Decision evidence and findings
Attachment B - Section 70 of TIA
Attachment C - Appeal Provisions
Attachment D - Permitted Road Access Location Plan
Page 3 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original