Essence of Peregian Beach Project v2
Environmental Management Plan (Construction and Operation)



1. Introduction

North Coast Environmental Services have been commissioned by Thomco No 2087 Pty Ltd to
prepare an Environmental Management Plan to manage impacts to the environmental values
associated with Lot 1 on SP286680; located at 215 David Low Way in Peregian Beach (referenced
hereafter as ‘the site’). The impacts are anticipated to arise as a result of the approved construction
of 19 x 3+ bedroom units, one (1) manager’s unit and a motel building containing 32 units. The site
is proposed to be reconfigured from one (1) Lot into three (3) Lots (MCU16/0153 REC16/0041).
The site layout has been prepared by Reddoor Architecture (refer Attachment A).

2. Purpose of This Report

This Environmental Management Plan (EMP) (Construction and Operation) has been prepared to
assist Thomco No. 2087 Pty Ltd (Thomco) and/or their nominated Construction Contractor, and
other parties associated with the Essence of Peregian Beach development works, in discharging
their statutory responsibilities relating to environmental matters during the construction and
operation phase of the Project. This EMP includes specific environmental management actions,
which have been detailed in Table 1 of this document.

The following potential environmental issues have been identified in this EMP as key areas for
consideration during the construction and operation phase of the Project:

    •    Legislative compliance
    •    Fauna and fauna habitat;
    •    Vegetation management;
    •    Water quality (including groundwater);
    •    Erosion and sediment control; and
    •    Weed control and pest management.

Other issues that have been considered in this EMP include:

    •    Waste management;
    •    Fuels and hazardous materials;
    •    Air quality and dust control;
    •    Aboriginal cultural heritage;
    •    Noise and vibration; and
    •    Visual amenity

3. Statutory and Policy Requirements

Thomco and all members of the project team have a “General Environmental Duty” under Section
319 of the Environmental Protection Act 1994 (EP Act). The General Environmental Duty makes
it an offence under the Act to carry out any activity that causes, or is likely to cause, environmental
harm unless all reasonable and practical measures have been taken to prevent or minimise the
potential harm.

To minimise environmental harm, it is necessary to assess what environmental conditions exist
on-site and to identify potential environmental impacts of the proposed development. In addition
to the EP Act, all development must comply with the relevant provisions of Commonwealth and
State Legislation including but not limited to:

    •    Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)
         (Commonwealth);
    •    Planning Act 2016 (Planning Act);
    •    Nature Conservation Act 1992 (NC Act);

© 2019 - J000488                                                                                     1
Log in to download the original file

EMP v2 - ESSENCE OF PEREGIAN 215 DAVID LOW WAY, PEREGIAN BEACH.PDF · 1.7 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.