R5304: NOOSA RESOURCE RECOVERY CENTRE - STORMWATER MANAGEMENT PLAN



5                SITE INSPECTION AND MONITORING
SMPs should be considered live documents that in some instances will require review and updating as site conditions
change, or if the adopted measures fail to achieve the required treatment standard.

Site inspections and monitoring are to be undertaken as detailed below. When a site inspection detects a notable failure
in the adopted drainage or other ESC measures, the source of this failure must be reported, investigated and appropriate
amendments made.

Best practice site management requires all ESC measures to be inspected at the following frequencies and include the
following checks as a minimum:

Daily site inspections (during rainfall)
       +      All drainage, erosion and sediment control measures
       +      Occurrences of excessive sediment deposition (whether on-site or off-site)
       +      All site discharge points (including dewatering activities as appropriate)
Weekly site inspections (even if work is not occurring on-site)
       +      All drainage, erosion and sediment control measures
       +      Occurrences of excessive sediment deposition (whether on-site or off-site)
       +      Occurrences of litter or sediment placed, deposited, or washed from the site, including deposition by vehicular
              movements
       +      Oil, fuel and chemical storage facilities
Following runoff producing rainfall (within 18 hours of rainfall event)
       +      All drainage, erosion and sediment control measures
       +      Occurrences of excessive sediment deposition (whether on-site or off-site)
       +      Occurrences of litter or sediment placed, deposited, or washed from the site, including deposition by vehicular
              movements




Environment. Engineering. Education.                                                                                  PAGE 14

Used in these records

About this file

File size
19.4 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 8 - Interim Stormwater Management Plan - TOPO.pdf · 19.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.