Original source · versioned page text
Amended Referral Agency Response - Planning - RAP22 0023 01 (As Published)
15. All easements must be designed in accordance with the planning scheme and granted
at no cost to the Grantee. Where the Grantee is Council or a service authority, the
easement documentation must be in accordance with the Grantee’s standard easement
terms. Draft easement documentation must be submitted to Council for endorsement.
16. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
17. All earthworks and associated structures/batters must be undertaken in accordance with
an Operational Works. All earthworks and associated structures/batters, both above and
below ground level, both temporary and permanent must be contained entirely within
the subject site unless written permission from the respective landowner(s) is provided
to Council.
18. Prior to the issue of an Operational Works permit for Earthworks, an Acid Sulfate Soils
Assessment and Management Plan and a site-specific Dewatering Plan must be
prepared, submitted and accepted by Council. The Acid Sulfate Soil Assessment and
Management Plan and the Dewatering Plan must be prepared by a suitably qualified
person (RPEQ) and must include but not be limited to:
a. sufficient detail to demonstrate how acidic water encountered during excavation and
construction will be treated and disposed of; and
b. sufficient detail to demonstrate that the dewatering of the site will not impact on the
structural integrity of buildings and structures on adjoining properties.
19. All retaining walls must be designed and constructed in accordance with the planning
scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining
walls that are publicly accessible and exceed 1.0m in height must be fitted with a
commercial grade safety fence.
Damage to Services and Assets
20. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
2. REASONS FOR REFERRAL AGENCY’S DECISION
The proposal is subject to specific built form parameters outlined in The Noosa Plan.
3. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form
part of the referral agency conditions:
Development Compliance Inspection
1. Prior to the commencement of the use, please contact Council's Development
Assessment Branch to arrange a Development Compliance Inspection.
Page 4 of 6
Document Set ID: 24695056