 29 September 2023


                •    Provision of spill / pollution control equipment that is readily accessible to clean up
                     spills and leaks.
                •    Ensure spill/pollution control measures are available and maintained in working
                     condition.
                •    Sediment contained by the sediment control devices such as sandbags, sediment
                     fences and containment bunds must be frequently removed and placed in a
                     controlled area.
                •    Implement an inspection schedule for any spill or leaks of any potential polluting
                     areas or activities.

4.7.4 Erosion Sediment Control Management Goals

    •     Licenses, approvals, permits and inspection reports are in order.
    •     Sediment or pollution control devices such as sandbags, sediment fences and containment
          bunds are in place, maintained and effective.
    •     Spill/ pollution control equipment is readily accessible at designated locations.
    •     No accumulated sediment is contained by the sediment control devices such as hay bales,
          sediment fences and containment bunds.
    •     No sediment exceeding a depth of 300mm in the pollution control devices (e.g. silt trap).

4.7.5 Erosion and Sediment Control Implementation Program

    •     Licenses, permits or approvals for each environmentally relevant activity must be obtained
          prior to the commencement of the particular activity.
    •     Appropriate control measures such as sediment fences, temporary construction entry/ exit
          sediment traps, pollution containment devices (e.g. sandbags), stormwater diversion and
          administrative controls must be installed and established prior to commencement of the
          earthworks and construction activities.
    •     Pollution control devices such as spill control equipment must be inspected on a regular
          basis (at least weekly).
    •     Other sediment and pollution control equipment such as containment bunds, hay bales and
          sediment fences must be inspected on a regular basis (at least daily).
    •     Inspection for any leaks, spills or potential contaminating activity must be performed on a
          regular basis (at least daily).
    •     Remove accumulated sediment or other contaminants from sediment/ pollution control
          devices on a regular basis.
    •     All erosion and sediment control measures must be inspected within 24 hours of expected
          rain and within 18 hours of a rainfall event.

4.7.6 Responsible Person Or Organisation

The contractor shall be responsible for the implementation and maintenance of the Erosion and
Sediment Control Measures.




 Excellence with Economy in Engineering                                                                        17
 https://mpncnetau.sharepoint.com/sites/administration/shared        documents/9000-9999/9900-
 9999/9954/report/29-09-23 stormwater management plan_issue a.docx
Log in to download the original file

Appendix D- SWMP.pdf · 13.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.