5. CONCLUSION
This Stormwater Management Report has outlined how the stormwater run-off from the site
is to be managed to comply with the relevant requirements and minimise any adverse
impacts to the downstream catchments.
• The existing site and upstream catchments’ drainage patterns currently discharge
from the site as overland flows into towards Lake Doonella to the south of the site.
• The proposed legal point of discharge for the site will continue to be Lake Doonella.
• The existing and proposed development site have been modelled for the critical
design storm events for the site, which found attenuation would be required. Further
modelling for the mitigated developed site was able to demonstrate that there will
be no increase to total existing discharge conditions from the site for any of the storm
events.
• During construction, erosion and sediment control measures shall be implemented
to minimise potential contaminants impacting the downstream receiving
environment. An erosion and sediment control plan shall be developed as part of a
submission for Operational Works approvals.
• In the operational phase of the development, a stormwater treatment train will
provide quality improvements as required by the Noosa Council Planning Scheme
Policy. Roof run-off is to be directed towards 4 x 3,000L rainwater reuse and
attenuation tanks that will be fitted with first-flush divertors to will divert initial roof
run-off to on site irrigation of vegetated areas. The tanks are to be plumbed for reuse
for internal (laundry and toilets) purposes that will serve to provide both treatment
and reduce the volume of run-off leaving the site. Overflows from the tanks, as well
as the piped drainage will be directed toward the 6.5m2 bioretention areas at the
south of each site that will treat the majority of run-off from the site while also
attenuating run-off volumes. Ocean Protect Ocean Guard litter baskets will be
provided to the pits within the driveway areas to provide at source primary
treatment. Outflows from the bioretention area will be via a surcharged drainage line
from each area, using a one-way flap gate outlet to prevent backflows.
By implementing the proposed stormwater treatments, the development will reduce
the quantity of stormwater pollutants by more than 90% of gross pollutants, 80% of
total suspended solids, 60% total phosphorous and 45% total nitrogen, exceeding
the pollutant reduction targets required for the site.
• By implementing the proposed stormwater solution, it is considered that stormwater
layout proposed will minimise any adverse impacts to the downstream environment
arising from the stormwater run-off while also meeting the stormwater quality targets
required for the development.
Page 18 of 22
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.